Determining the Level of Design Culpability in Construction Contracts
Info: 32281 words (129 pages) Dissertation
Published: 20th Jan 2022
Abstract
Despite preceding case law, scholarly journals and current legislation, the issue of design culpability applicable to construction contracts remains an issue, as disputes continue to be raised in court. The study investigated and addressed the issue, with the focus on whether design responsibility can be clearly delineated by the contractual parties to precisely define the contractual provisions at the time the contract is formed, and deliver certainty. The research strategies recognised design culpability as a conflicting obligation, embedded into industries contracts. Whilst the standards of care have the potential to fairly apportion responsibility, vague contractual terms lead to unclear intent, causing resistance between project stakeholders. It is, therefore, essential that the contractual parties liable for design realise their obligations and have a mutual understanding and interpretation of the contractual clauses.
Key Words: Design Culpability, Contract Law, Reasonable Skill and Care, Fit for Purpose, Contractor’s Designed Portions (CDP), Design and Build, Disputes
Table of Contents
Click to expand Table of Contents
1.0 Introduction
1.1 Background
1.2 Rationale
1.3 Hypothesis
1.4 Research Aim
1.5 Research Objectives
1.6 Research Findings
1.7 Guide to Study
1.7.1 Chapter 1: Introduction
1.7.2 Chapter 2: Literature Review
1.7.3 Chapter 3: Methodology
1.7.4 Chapter 4: Data Collection and Analysis
1.7.5 Chapter 5: Conclusion and Recommendations
2.0 Literature Review
2.1 Introduction
2.2 UK Construction Industry Context
2.2.1 The Industry
2.2.2 Professionalism in Construction
2.2.3 The Nature of Projects
2.3 Design Culpability
2.3.1 Implied Contractual Obligations of the Design Team
2.3.2 Implied Contractual Obligations of the Contractor
2.3.3 Distinctive Levels of Liability
2.3.4 Fitness for Purpose: Sale of Goods Act
2.3.5 Insurance
2.3.6 The Law of Contract and Tort
2.4 Construction Contracts
2.4.1 The Joint Contract Tribunal 2016
2.4.2 NEC Engineering and Construction Contract 2013
2.4.3 Traditional Procurement
2.4.4 Contractor’s Designed Portions (CDP)
2.4.5 Design and Build Procurement
2.5 Chapter Summary
3.0 Methodology
3.1 Introduction
3.2 Narrowing Down the Research Topic
3.3 Research Classification and Strategy Approaches
3.3.1 Quantitative Research
3.3.2 Qualitative Research
3.3.3 Quantitative vs. Qualitative Research
3.3.4 Triangulated Research
3.3.5 Research Design
3.4 Adopted Data Collection Methods and Justification
3.4.1 Questionnaires
3.4.2 Interviews
3.5 Limitations of Research
3.6 Ethical Considerations
3.7 Chapter Summary
4.0 Data Collection and Analysis of Results
4.1 Introduction
4.2 Analysis of Questionnaire Survey
4.2.1 Introduction
4.2.2 Profile of Survey Participants
4.2.3 Classifying Culpability
4.2.4 The Importance of Managing Design
4.2.5 Prominent Issues During the Construction Phase of Work
4.3 Analysis of Interviews
4.3.1 Introduction
4.3.2 Profile of Interview Participants
4.3.3 Classifying Culpability
4.3.4 The Importance of Managing Design
4.3.5 Prominent Issues During the Construction Phase of Work
4.3.6 Lack of Quality Design Information Impeding the Contractor’s Performance
4.3.7 Requirements at Tender Stage
4.4 Chapter Summary
5.0 Conclusions and Recommendations
5.1 Introduction
5.2 Summary of Research Findings
5.2.1 Literature Review
5.2.2 Questionnaires
5.2.3 Interviews
5.3 Review of Research Objectives
5.3.1 Objective 1
5.3.2 Objective 2
5.3.3 Objective 3
5.3.4 Objective 4
5.3.5 Objective 5
5.4 Recommendations to Industry
5.5 Limitations of the Study
5.6 Recommendations for Further Research
References
Appendices
REQUIRED APPENDICES
Appendix A: Project Definition Document & Gantt Chart
Appendix B: Health and Safety Risk Assessment
Appendix C: Ethical Clearance Email
Appendix D: Participant Information Sheet
Appendix E: Blank Informed Consent DISSERTATION APPENDICES
Appendix F: Questionnaire Survey Questions
Appendix G: SPSS (Statistical Package for the Social Sciences) Data Tables
Appendix H: Telephone Interview Transcripts
List of Tables
Table 2.1: DESIGN CULPABILITY IN CONSTRUCTION CONTRACTS
Table 3.1: PRINCIPLES OF QUESTIONNAIRE CONSTRUCTION (ADAPTED FROM NAOUM, 2013, P.60)
Table 3.2: COMPARISON BETWEEN A POSTAL SURVEY AND INTERVIEW TECHNIQUE (ADAPTED FROM TASHAKKORI AND TEDDLIE, 2002, P.303)
Table 3.3: INTERVIEW TYPES (ADAPTED FROM NAOUM, 2013, P.55 & 56)
Table 4.1: ORDINAL SCALE RESPONSE CODING
Table 4.2: DEMOGRAPHIC PROFILE OF SURVEY PARTICIPANTS
Table 5.1: DEMONSTRATION OF INCREASING CORRELATIONS(Q5, Q6, Q10, Q11, Q13)
List of Figures
Figure 1.1: RESEARCH APPROACH (ADAPTED FROM RAMACHANDRA, 2013, P.66)
Figure 2.1: LIABILITY SPECTRUM (GAAFAR AND PERRY, 1999, P.306)
Figure 3.1: THE NARROWING DOWN OF THE RESEARCH TOPIC (NAOUM, 2013, P.11)
Figure 3.2: TRIANGULATION OF QUALITATIVE DATA (FELLOWS AND LIU, CITED IN AMARATUNGA ET AL., 2002, P.24)
Figure 3.3: ILLUSTRATION OF DATA COLLECTION METHODS TO ACHIEVE THE FORMULATED OBJECTIVES
Figure 4.1: ISSUES DURING THE CONSTRUCTION PHASE (Q12)
List of Abbreviations
AEDM Architectural Engineering and Design Management
CDP Contractor’s Designed Portions
D&B Design and Build
ER Employer’s Requirements
JCT The Joint Contracts Tribunal
OGC Office of Government and Commerce
NEC The New Engineering Contract
SD Standard Deviation
SBC Standard Building Contract
SBC/Q Standard Building Contract with Quantities
SPSS Statistical Package for the Social Sciences
TCC Technology and Construction Court
TR Technical Requirements
Table of Cases and Statutes
Note: the page numbers for which cases are referred to have been shown in brackets at the end of each entry.
Bolam v Friern Hospital Management Committee [1957] QB, 1 WLR 582 (QB) (16)
Brunswick Construction Ltd v Nowlan [1974] SC, 21 BLR 27 (SC) (26)
Cooperative Group Ltd v John Allen Associates Ltd [2010] QB, EWCH 2300 (QB) (18)
Cooperative Insurance Society Ltd v Henry Boot (Scotland) Ltd (Costs) [2002] QB, EWHC 1270 (QB) (30)
Donoghue v Stevenson [1932] HL, AC 562 (HL) (27)
Esso Petroleum Co v Mardon [1957] CA, 2 WLR 583 (CA) (27)
George Wimpey & Co Ltd v DV Poole and Others [1984] QB, 128 SJ 969 (QB) (26)
Greaves & Co (Contractors) Ltd v Baynham Meikle & Partners [1975] CA, 3 ALL ER 99 (CA) (17,22,25)
IBA v EMI Electronics Ltd and BICC Construction Ltd [1980] HL, 14 BLR 1 (HL) (22)
John Mowlem & Co v British Insulated Callenders Pension Trusts Ltd and Others [1970] DC, 3 CON LR 63 (DC) (30)
Lanphier v Phipos [1838] CP, 173 ER 581 (CP) (23)
Lindenberg v Joe Canning and Others [1992] QB, 62 BLR 147 (QB) (23)
Merton LBC v Lowe & Another [1981] CA, 18 BLR 130 (CA) (18)
Moresk Cleaners Ltd v Hicks [1966] QB, 4 BLR 50 (QB) (17,18)
MT Højgaard A/S v EON Climate and Renewables UK Robin Rigg East Ltd [2015] CA, BLR 431 (CA) (20)
Murphy v Brentwood DC [1990] HL, AC 398 (HL) (27)
Plant Construction Ltd v Clive Adams Associates and JMH Construction Services Ltd [2000] CA, BLR 137 (CA) (23)
Pratt v George J Hill Associates [1988] CA, 38 BLR 25 (CA) (18)
Prier v Refrigeration Engineering Company [1968] SC, 442 621 (SC) (27)
RM Turton & Co Ltd (In Liquidation) v Kerslake & Partners [2000] CA, 3 NZLR 406 (CA) (23)
Sale of Goods Act 1979 Supply of Goods and Services Act 1982
Tai Hing Cotton Mills v Liu Chong Hing Bank [1985] PC, AC 80 (PC) (27)
Viking Grain Storage Ltd v T H White Installations Ltd and Another [1985] QB, 33 BLR 103 (QB) (22)
Walter Lilly & Co Ltd v Mackay [2012] TCC, EWHC 1972 (TCC) (29)
Young & Marten Ltd v McManus Childs Ltd [1968] HL, 3 WLR 630 (HL) (21)
1.0 Introduction
This chapter highlights the developments of the research problem through addressing the aim and objectives, methodology undertaken and the key findings.
1.1 Background
The detrimental effects unclear contractual provisions, regarding design culpability, have on construction projects and the stakeholders involved, have been highlighted in leading case law and widely acknowledged industry reports and journals over the last 30 years:
- Viking Grain Storage Ltd v T H White Installations Ltd and Another [1985] QB, 33 BLR 103 (QB) (22)
- Limitation of Design Liability for Contractors – Gaafar and Perry (1999)
- Contract Theory and Contract Practice: Allocating Design Responsibility in the Construction Industry – Carl J Circo (2006)
- Design Liability: Problems with Defining Extent and Level – Sarah Lupton (2015)
- MT Højgaard A/S v EON Climate and Renewables UK Robin Rigg East Ltd [2015] CA, BLR 431 (CA) (20)
- The National Construction Contracts and Law Survey (2015)
The issues do not arise solely due to design culpability, but the contractual conflicts and disputes that ascend from the ambiguous performance obligations and contingent contracts. Kraus and Scott (2009) highlight the importance of, “honouring the contractual intent of the parties” (p.1). However, little academic attention has been given to the, “structure of contractual intention” (p.1). It has been recognised that courts now ask, “how a reasonable person would have understood her partner’s intention at the time of contracting” (p.1). A potential weakness with the delineation of design responsibility, is accurately defining and appointing it. Therefore, it is crucial that as the contractual agreements are formed, culpability is mutually agreed with declarations of who is liable for what.
When writing up legally enforceable contracts, the parties must select the contractual provisions and can outline vague or precise terms (Hermalin, 2008). Vague terms endeavor to use the courts to allocate a concrete definition to these phrases, if the case is adjudicated, to allow for interpretation. The parties may not be obliged to specify exact obligations at the time the contract is formed, however, these phrases may provide reason for dispute. Precise terms obviate the requirement of the courts input, enforcing the explicit and accurate obligations the parties have stipulated in advance of adjudication.
Although, Hermalin (2008) illustrates how often difficulties may arise in, “precisely describing potentially relevant contingencies” (p.1) as the contract is written up. This research seeks to understand and explore how design culpability is set out within construction contracts and the level at which this liability is assigned to key stakeholders. Furthermore, it aims to analyse relevant case law that appraises the delineation of design culpability and provide a framework to determine the level of design responsibility applicable to construction contracts.
1.2 Rationale
Hermalin (2008) suggests that “vagueness of language” and, “the difficulty of precision” (p.2) may impede efficient contracting due to incomplete provisions. He went on to say, “if it is difficult to describe contractual contingencies, then how do the parties to the contract necessarily communicate their intentions to each other?” (p.24). These vague terms can often be the foundation for disputes and, “hinder the smooth execution of contracts” (Lai, Yik, and Jones, 2004, p.51). Therefore, “a clear definition of the responsibilities of the contracting parties is crucial” (p.44). The underlying principle of this research is to gather professional perspectives from lead contractors to ascertain the implications of vague design culpability and perceived work scopes in the UK construction industry.
1.3 Hypothesis
The research hypothesis is: ‘The clear delineation of design responsibility will require the contractual parties to precisely define the contractual contingencies at the time the contract is formed, as well as ensure the stakeholders have the same intentions and understanding of these provisions’.
1.4 Research Aim
The aim of this research study is to provide a framework to determine the level of design culpability applicable to construction contracts.
1.5 Research Objectives
To achieve the research aim, there are five objectives:
- To assess construction contracts;
- To review key roles of responsibility for design in contracts;
- To analyse case law which appraises the delineation of design responsibility in construction contracts;
- To explore companies and project stakeholder’s views concerning design culpability within projects and contracts, and
- Produce guidance on understanding design responsibility.
1.6 Research Findings
Key findings of the study are as follows:
- Construction contracts required the contractual parties to precisely define the contract provisions as the contract is formed to avoid misunderstanding;
- Where contractor’s design portions are concerned, interfaces between CDP and non-CDP elements require attention to highlight lines of responsibility;
- A spectrum of liability is required to develop industries understanding;
- For use at tender stage, a template should be developed to expose outstanding design information;
- Design and build contracts need to adapt to offer the capability to manage complex designs and/or high level finishes, and
- There is a lack of suitably qualified design managers to cope with their increasing demand.
1.7 Guide to Study
1.7.1 Chapter 1: Introduction
Provided an overview of the research problem and current knowledge and perspectives, highlighting the background and rationale to the study. The hypothesis, aim and objectives and key findings were identified. The Project Definition Document can be found in Appendix A along with an effective time-management strategy.
1.7.2 Chapter 2: Literature Review
Analytical and critical appraisal of current literature and case law related to the research study. The chapter presented industry context, followed by recognition of design culpability applicable to various construction contracts and project stakeholders.
1.7.3 Chapter 3: Methodology
The chapter classified the strategic approaches available and outlined the research method adopted (as shown in Figure 1.1), which was relevant to the solution of the defined problem. It identified the limitations of the research along with establishing the credibility and ethical values adhered to.
1.7.4 Chapter 4: Data Collection and Analysis
Documented the analyses and findings from the questionnaire survey and telephone interviews, in line with the literature findings, research problem and objectives (section 1.5), to identify key themes and patterns.
1.7.5 Chapter 5: Conclusion and Recommendations
A series of concluding results were formed in conjunction with the literature findings, research problem and the set of objectives (section 1.5). Following a provision of recommendations to the industry, limitations of the study and recommendations for further research.
Figure 1.1: Research Approach (Adapted from Ramachandra, 2013, p.66)
2.0 Literature Review
2.1 Introduction
This chapter aims to establish the context for the research by reviewing literature surrounding the allocation of design culpability within a construction contract. A review of the UK construction industry, construction contracts and key project stakeholders’ roles and responsibilities in relation to design culpability will be critically appraised. Throughout the chapter, relevant case law will be analysed as well as leading publications to demonstrate the level of understanding and guidance around design culpability.
2.2 UK Construction Industry Context
2.2.1 The Industry
The industry is highly complex (McDonnell, 2013), interlinking key stakeholders such as consultants, clients, and contractors. A construction project team involves a string of professionals, specialists, and suppliers, each a unique collection of participants appointed for the project’s needs; their professional expertise guide a project to completion. It is, therefore, essential to understand construction contracts, not only as standard forms but also as documents that are flexible, allowing for clause adaptations, to meet the needs and demands of each individual scheme.
Waterhouse, Peckett, Malleson and Beaumont (2015) highlight complying with lawful responsibilities, along with having the appropriate clauses in place to deal with construction disputes, as fundamental procedures to aid a smooth construction process. McDonnell (2013) agrees, depicting detailed contractual terms which appropriately allocate risk and responsibility as significant measures.
2.2.2 Professionalism in Construction
Many scholarly journals base their view of professionalism on individual characteristics and behaviours. However, Martimianakis, Maniate, and Hodges (2009) suggest a focus on these alone, “is insufficient as a basis on which to build further understanding of professionalism” (p.829). Professionalism can be further defined by personal characteristics, ethics and diversity (Martimianakis, Maniate, and Hodges, 2009). To enhance professionalism within the industry, numerous organisations have direct links with higher education, supporting individuals on academic courses gaining qualifications. (Hughes, Murdoch and Champion, 2015). This close involvement enables the industry to develop and continually build on its corpus of knowledge.
2.2.3 The Nature of Projects
Hughes et al. (2015) suggest that commercial risk and project teams are, “the most significant defining characteristics of projects and project strategies” (p.8). Each construction project is unique, thus increasing inherent risks. These risks need to be appropriately managed to ensure the project is completed to the required quality, within time and on the budget. A construction project could be described as a puzzle in relation to the parties who form the temporary organisational structure. A scheme will piece together various specialist skills and groups of people to form a project team, who will all eventually disengage their duties upon completion of their requirements (Hughes et al., 2015). Thus, pieces of the puzzle will come and go throughout the duration of a project, a factor that gives rise to its constantly changing environment.
2.3 Design Culpability
Victor O. Schinnerer and Company Inc. (2017) refer to design responsibilities as obligations which are enforceable at law, “arising out of the performance of, or failure to perform, professional services by the design professional” (Victor O. Schinnerer and Company Inc., 2017, p.2). Traditional contractual relationships would see the client entering two separate contracts for the design and construction phases of work. However, modern tendencies have seen a lean towards both bespoke and design and build contracts, where the contractor is burdened with obligations for both design and construction.
The National Construction Contracts and Law Survey 2015 developed a questionnaire to identify which procurement methods were most frequently used by contractors over that past 12 months, which highlighted that design and build procurement was selected by 49%, as opposed to traditional procurement by 34% of respondents (Waterhouse et al., 2015, p.10). Express provisions within a construction contract detail both the design teams and contractor’s obligations under the contract, outlining the level of responsibility delineated in respect of the design.
2.3.1 Implied Contractual Obligations of the Design Team
2.3.1.1 Level of Culpability
The decisions held in Bolam v Friern Hospital Management Committee[1], confirm that professional designers are required to use ‘reasonable skill and care’: “Where you get a situation which involves the use of some special skill or competence, then the test as to whether there has been negligence or not is … the standard of the ordinary skilled man exercising and professing to have that special skill. A man need not possess the highest expert skill; … it is sufficient if he exercises the ordinary skill of an ordinary competent man exercising that particular art”[2].
However in Greaves & Co (Contractors) Ltd v Baynham Meikle & Partners[3], the structural engineers were held liable for a higher standard of care due to an implied contractual term that required the design to be fit for its intended purpose. Without this term though, the engineers would have been culpable for negligence, breaching their duty to use reasonable skill and care as competent, professional persons. It, therefore, should be highlighted that assumptions cannot be determined regarding implied obligations of the designer: “The law does not usually imply a warranty that [a professional] will achieve the desired result, but only a term that he will use reasonable care and skill. The surgeon does not warrant that he will cure the patient. Nor does the solicitor warrant that he will win the case”[4].
2.3.1.2 Delegation of Design Work
Hughes et al. (2015) advise that the architect has single point responsibility for the design of the work, and without authority to delegate items of this work, he will be personally responsible for all defects, as held in Moresk Cleaners Ltd v Hicks[5]. Where a consultant has signed up to design works that have developed into areas they do not strictly have the necessary knowledge or skills to carry out to the required detail, they are faced with a problem. The judged ruled in Moresk that: “An architect who lacks the ability or expertise to carry out part of a design job has three choices:
- To refuse the commission altogether;
- To persuade the employer to employ a specialist for that part of the work, or
- To employ and pay for a specialist personally, knowing that any liability for defective design can then be passed along the chain of contracts”[6].
In this case, an architect was employed to prepare plans and specifications for an extension to Moresk’s laundry. The architect delegated design work to a subcontractor, and when a claim was brought against him in court, he argued that it was an implied term in his contract that he had the authority to delegate design. However, if a professional is appointed to carry out design works and accepts the contract, he is agreeing he can provide such works himself. The court found no such implied term existed within the contractual provisions and stated, “if a building owner entrusts the task of designing a building to an architect, he is entitled to look to that architect to see that the building is properly designed”[7].
Due to the evolving nature of projects and modern construction technology, which have increased in complexity and speciality, there are a greater chance employers will give architects the authority to delegate works (Hughes et al., 2015). Thus, leading to, “an increased dependence on specialists at both the design and construction stages of a project” (p.205). Cooperative Group Ltd v John Allen Associates Ltd[8] considered the designer’s reliance on guidance from another professional, “construction professionals did not by the mere act of obtaining advice or a design from another party thereby divest themselves of their duties in respect of that advice or design”[9]. The case went on to review Merton LBC v Lowe & Another[10], where the architect was given entitlement to delegate design, unlike in Moresk, which held that when given the authority, they owe a duty of care to their employer, “construction professionals could discharge their duty to take reasonable care by relying on the advice or design of a specialist if they acted reasonably in doing so”[11].
This does not make the architect liable for defects in their specialists work, but if they negligently recommended the use of their skill set, they could potentially be liable for their employer’s losses (Hughes et al., 2015). As held in Pratt v George J Hill Associates[12], the defendant architect was held liable after claiming that a contractor was suitable, though in practice they were not. The contractor became insolvent, and the architect was liable to the client for the money they were unable to recover from the contractor due to their recommendation.
2.3.2 Implied Contractual Obligations of the Contractor
2.3.2.1 Level of Culpability
The NEC Engineering and Construction Contract 2013 permits the contractor to rebut a liability presumption if optional clause ‘Option X15’ is invoked. This clause limits the contractor’s liability for his design to reasonable skill and care, “the Contractor is not liable for defects in the works due to his design so far as he proves that he used reasonable skill and care to ensure that his design complied with the Works Information” (Institution of Civil Engineers, 2013, p.52). The implementation of this clause allows the contractor to prove his non-negligence where there is a fault to escape liability.
However, a strict liability will be imposed upon the contractor if this clause is not invoked, to guarantee that the design will be fit for its intended purpose. Without proving he used reasonable skill and care, he will be liable for defects in the works due to his design. The burden of proof is reversed in this case, whereby the contractor is guilty until proven innocent. In both JCT’s Design and Build Contract 2016 and SBC/Q Standard Building Contract with Quantities 2016, there is a similar clause relating to the completion of design work.
Article 1 under the design and build contract states that, “the Contractor shall complete the design for the Works” (The Joint Contracts Tribunal, 2016, p.3) and under the SBC/Q contract, clause 2.2.1 states, where the works include a Contractor’s Designed Portion, the contractor shall, “complete the design for the Contractor’s Designed Portion” (The Joint Contracts Tribunal, 2016, p.33). ‘Complete’notions that the contractor is required, where he is taking on a design, to satisfy himself that the design and/or works are fit for purpose. Determining the standard of care owed by the contractor in a design and build contract presents a challenge given their dual role.
In JCT’s Design and Build Contract 2016, clause 2.17.1 states: “Insofar as his design of the Works is comprised in the Contractor’s Proposals and in what he is to complete in accordance with the Employer’s Requirements and these Conditions (including any further design that he is required to carry out as a result of a Change), the Contractor shall in respect of any inadequacy in such design have the same liability to the Employer, whether under statute or otherwise, as would an architect or other appropriate professional designer who holds himself out as competent to take on work for such design and who, acting independently under a separate contract with the Employer, has supplied such design for or in connection with works to be carried out and completed by a building contractor who is not the supplier of the design” (The Joint Contracts Tribunal, 2016, p.35).
Virtually the same clause as above is present in the JCT’s SBC/Q Standard Building Contract with Quantities 2016, clause 2.19.1 p.38, to define design liabilities where there is a Contractor’s Designed Portion. However, “express terms can override the normal default” (Lupton, 2015, p.102). The standard of care applicable to design and build contractors has been subject to review and analysis since its development in the modern construction industry. Barry Joseph Miller (1982) recommended that a sole fitness for purpose standard of care should be implied when a contractor is engaged in both, “transactions” (p.132) allowing for uniformity.
This could be perceived as unfair, as a lower standard is enforced on a professional designer carrying out only design under a traditional form of contract. They are required to carry out design work with reasonable skill and care, and therefore, if the designer can prove he has done so, and the construction works fail, the contractor will be held accountable for not providing works that are fit for purpose. He cannot shift this culpability back onto the design team if they produced their design work with reasonable skill and care. However, clause 2.17.1 and clause 2.19.1 (referenced above) seek to address this issue, with a clear demarcation between the design and construction phases.
The clause denotes that for the design phase of work, the contractor has the ‘same liability’, as would a professional designer, in contrast to Miller’s beliefs. Therefore, the contractor is only required to carry out their design services with reasonable skill and care. It is only for the construction phase of work that the contractor will have to attain a fitness for purpose standard. Exclusive of this clause, the contractor is obligated to deliver both design and construction works fit for purpose.
These clauses set out to limit culpability, however, they could be amended, as demonstrated by the National Rail 10 Schedule of Amendments (Network Rail, 2016): “2.17.1 Insofar as the design of the Works is comprised in the Contractor’s Proposals and in what the Contractor is to complete in accordance with the Employer’s Requirements and these Conditions (including any further design which the Contractor is to carry out because of a Change), the Contractor warrants and undertakes to the Employer that: 2.17.1.1 he has exercised and will continue to exercise in the design of the Works all the reasonable skill, care and diligence to be expected of a professionally qualified and competent architect, engineer or other appropriate consultant considering the size, scope, nature, type and complexity of the Works; 2.17.1.2 the Works will, when completed, comply with any performance specification or requirement included or referred to in the Employer’s Requirements or the Contractor’s Proposals”.
Both standards of care co-exist in this clause, which supports Mr. Justice Edwards-Stuart’s remarks in MT Højgaard A/S v EON Climate and Renewables UK Robin Rigg East Ltd[13]. He noted that “it is not uncommon for the two obligations … to exist side by side in construction contracts, as they are not mutually incompatible”. The court deliberated whether the contractor’s obligation was limited to using reasonable skill and care or whether it was under a strict obligation to achieve a service life of 20 years. The scheme of the Technical Requirements (TR) led the judges to believe that the 20-year design life was an intention, not a guarantee, which is dissimilar to a warranty to achieve that design life. Further to this, the TRs made no specific reference to a guarantee of 20 years. If it was a requirement, it should have been made patently obvious not, “tucked within the technical requirements”[14].
2.3.2.2 Workmanship and Materials
An implied fit for purpose obligation may arise on the part of the contractor, “in relation to goods and materials supplied” (The Joint Contracts Tribunal, 2013). In the case of Young & Marten Ltd v McManus Childs Ltd[15], the Court of Appeal held that: “There will be implied into a contract for the supply of work and materials a term that the materials used will be of merchantable quality and a further term that the materials used will be reasonably fit for the purpose for which they are used”.
The facts of the case stipulated this implied term as the contract sufficed to exclude it. The contractor installed tiles that were, “latently defective and thereby breached the implied term (of merchantable quality)”[16]. Further to this, a fitness for purpose obligation may arise where the employer makes known the exact intended purpose of the goods, “expressly or by implication” (The Joint Contracts Tribunal, 2013).
In Greaves, Lord Denning explained: “The owners made known to the contractors the purpose for which the building was required … to show that they relied on the contractors’ skill and judgment. It was, therefore, the duty of the contractor to see that the finished work was reasonably fit for the purpose for which they knew it was required. It was not merely an obligation to use reasonable care. The contractors were obliged to ensure that the finished work was reasonably fit for the purpose”[17].
It was Lord Scarman’s obiter remarks in IBA v EMI Electronics Ltd and BICC Construction Ltd[18], which affirmed a further implied term that can arise with regards to the entire completed structure: “In the absence of a clear, contractual indication to the contrary, I see no reason why one who during his business contracts to design, supply, and erect a television aerial mast is not under an obligation to ensure that is it reasonably fit for the purpose for which he knows it is intended to be used.
The critical question of fact is whether he for whom the mast was designed relied upon the skill of the supplier (i.e. his or his subcontractor’s skill) to design and supply a mast fit for the known purpose for which it was required”[19]. If the purpose of a design is made known, in line with the statutory law regulating the sale of goods (Sale of Goods Act, 1979), the designer accepts that the standard of care will be raised to a fit for purpose obligation.
In Viking Grain Storage Ltd v T H White Installations Ltd and Another[20], Judge John Davies QC questioned why the duty in relation to design should be any different than the standard expected for the quality of materials: “I find it difficult to comprehend why an entire contract to build an installation should need to be broken into so many pieces with differing criteria of liability. The virtue of an implied term of fitness for purpose is that it prescribes a relatively simple and certain standard of liability based on the reasonable fitness of the finished product irrespective of considerations of fault and of whether its unfitness derives from the quality of work or materials or design”[21].
2.3.2.3 Duty of Care
Construction professionals are legally required to carry out their services with a duty of care. As discussed by Thomas J in RM Turton & Co Ltd (In Liquidation) v Kerslake & Partners[22]: “It has been generally accepted that duty of care will arise where the relationship between the parties manifests the following criteria:
- The maker of the statement possesses a special skill;
- He or she voluntarily assumes responsibility for the statement and it is foreseeable that the recipient will rely on it;
- It is reasonable for the recipient to rely on the statement and he or she does so, and
- The recipient suffers loss as a result” (Adriaanse, 2016, p.278).
Emden stated in Binder VI (cited in Adriaanse, 2016), that: “It is thought that provided the contractor carries out work strictly in accordance with the contract documents, he is not responsible if the works prove to be unsuitable for the purpose which the employer and architect had in mind” (p.116). Though, if the contractor finds discrepancies in the design documentation, drawings and between the statuary provisions and the works, they are required to, under the JCT Design and Build Contract 2016, clause 2.13 and 2.17, report to the employer (The Joint Contracts Tribunal, 2016).
In Plant Construction Ltd v Clive Adams Associates and JMH Construction Services Ltd[23], the defendant appealed against an implied duty to warn for defective design, “of which it was aware but for which another party was responsible”. Failure to raise it caused the plaintiff to, “suffer economic loss”. Based on the decision held in Lindenberg v Joe Canning and Others[24], which held that where a contractor fails to raise concerns and proceeds with the contract he, “is in breach of an implied term that it would exercise the standard of care to be expected of an ordinary, competent building contractor”, Clive Adams Associates were held culpable.
2.3.3 Distinctive Levels of Liability
The standard of care for design is either an obligation to use reasonable skill and care or a guarantee that the design will be fit for its intended purpose. If reasonable skill and care are not achieved where required, the party is said to have been negligent (Marshall, 2011). Lupton and Cornes (2013) expand on Marshall’s statement by suggesting that the distinction between the two standards necessitates industries understanding as “in the former case negligence has to be shown whereas in the latter case there is an absolute obligation which is independent of negligence” (p.50).
Gaafar and Perry (1999) acknowledge that these overarching design principles may be due to an oversimplification subject to the lack of legal definition surrounding the two standards of care. Jackson and Powell (1992) sought to explain their position by reference to the case of Lanphier v Phipos[25], which initially expressed the standard of care over 100 years ago: “Every person who enters into a learned profession undertakes to bring to the exercise of it a reasonable degree of care and skill.
He does not undertake if he is an attorney that at all events you shall gain your case, nor does a surgeon undertake that he will perform a cure, nor does he undertake to use the highest degree of skill. There may be persons who have a higher education and greater advantages than he has, but he undertakes to bring a fair, reasonable and competent degree of skill”[26].
Holub’s (2017) study discusses how a professional is to provide a service with the “goal of achieving the desired result, but not a guaranteed result” (p.2). Design and construction professionals lack the control necessary to unequivocally guarantee the outcome of their services. It is unclear as to whether a design that is to be produced with reasonable care and skill should likewise be required to be fit for its purpose.
Fitness for purpose is seen to be the greater duty, Adriaanse (2016) endeavoured to define them: “A product or design may not be fit for its purpose without any allegation of fault. Where a particular purpose is made known by the employer, negligence need not be proven. All that had to be shown is that the particular purpose specified has not been achieved. As far as reasonable skill and care is concerned, it has to be proved that the design was negligent and that the designer did not use reasonable skill and care” (p.293).
2.3.3.1 Liability Spectrum
Gaafar and Perry (1999) state that the interpretation of fitness for purpose is dependent on the facts and circumstances of each case. The authors recommended that the industry develops a further understanding of what each level of design responsibility distinctly means, and expand the levels not only as two principles, but broadened into a scale that can be concisely drafted into contract clauses, as a robust solution in the prevailing legal and insurance contexts.
Figure 2.1: Liability Spectrum (Gaafar and Perry, 1999, p.306)
Figure 2.1 is a spectrum deduced from Gaafar and Perry’s research. The latter end of the spectrum ‘d’,demonstrates the contractor’s fitness for purpose liability. Here the intended purpose of the works needs to be clearly communicated by the client, as well as the requirements, to ensure this strict obligation is applied. On the opposite end of the spectrum ‘a’, the contractor will only be held liable to have exercised reasonable skill and care through their negligence. Most existing forms of contract, “attempt to limit the contractor’s liability to either boundary a or d” (p.307). Considering the decisions held in Greaves[27], Gaafar and Perry sought to explain how the determined liability may be placed at a point in-between the spectrum of ‘a and b’.
A professional designer is required to provide a design with reasonable skill and care, however, it was held that the contract stipulated that the defendant was required to take specific steps, “to discharge the duty to exercise reasonable skill and care” (p.305) which had not been taken. If they had been, it was said the design would have been fit for purpose. The spectrum between a and b implies that there may be circumstances in which, “reasonable skill and care may equate to fitness for purpose” (p.306), which corresponds to this decision. Boundary ‘c’ could occur anywhere between ‘b and c’, “in cases where higher skill and care may be interpreted by some practitioners as reasonable skill and care” (p.306), as held in George Wimpey & Co Ltd v DV Poole and Others[28].
George Wimpey aimed to persuade the court that they, “had been negligent on the basis that its special expertise meant it owed a higher duty of care than ordinary competence”. For the plaintiff to claim against his professional indemnity policy, he had to prove his negligence. A perceived problem is establishing the expected level of skill and care conceptualised by boundary ‘a’. If a party has been negligent, the courts have direct reasoning to hold the culpable party at fault for not exercising reasonable skill and care. Where there is potential consideration of negligence, the spectrum between ‘b and c’ is applied. And whereby higher skill and care is exercised, the level of liability lies between ‘c and d’. Brunswick Construction Ltd v Nowlan[29] demonstrates the highly critical nature of assuming a level of design culpability applicable to project stakeholders. In Brunswick, the contractor was held liable for a design defect, owing to his duty to warn, even though he had no direct responsibility for producing any of the design.
The case particulars were extreme, as the client relied entirely on the skill and judgement of the contractor, without any consultants to supervise. However, it proves that it is the specific circumstances of each project and contract that controls the liability applicable to a stakeholder, which can range anywhere from ‘a to d’. Gaafar and Perry’s (1999) notions outline design liability as a combination of factors that are all influenced by implied terms (from statute), clauses that form part of the contract and the manner in which these clauses and specifications have been written.
2.3.4 Fitness for Purpose: Sale of Goods Act
“English Law distinguishes between those who contract to supply a product and those who provide a service” (Adriaanse, 2016, p.276). The Sale of Goods Act 1979, under Section 14: Quality or Fitness, 14.3 states: “Where the seller sells goods in the course of a business and the buyer, expressly or by implication, makes known to the seller any particular purpose for which the goods are being bought, there is an implied condition that the goods supplied under the contract are reasonably fit for that purpose” (Sale of Goods Act, 1979). Both the Sale of Goods Act 1979 and Supply of Goods and Services Act 1982 further stipulate that “goods are of satisfactory quality if they meet the standard that a reasonable person would regard as satisfactory” (Supply of Goods and Services Act, 1982).
2.3.5 Insurance
Fitness for purpose obligations are commonly implied into building contracts, however, they can be the root cause of disruptions and disagreements between parties. This is due to the improbable position that contractors and professionals alike will be able to obtain professional indemnity insurance for such an obligation (Gaafar and Perry, 1999). If contractors are posed with it, it leaves them with a lacuna uninsured risk.
2.3.6 The Law of Contract and Tort
The Court of Appeal held in Esso Petroleum Co v Mardon[30] that where the “same set of facts amount to a breach of contract and tort, the plaintiff could choose in which action to frame a claim” (Adriaanse, 2016, p.276). This put the plaintiff in a better position, as the limitation period in the law of tort is longer than that in the law of contract, “since a tort action can be brought when the limitation period in the contract has expired” (Adriaanse, 2016, p.276). However, this decision was superseded in Murphy v Brentwood DC[31] initially retreated in Tai Hing Cotton Mills v Liu Chong Hing Bank[32], where Lord Scarman said that, “there … (is no) advantage to the development of the law in searching for a liability in tort where the parties are in a contract” (Adriaanse, 2016, p.276).
Professionals must comply with their appointment, and collateral warranties are in place to help remedy defective building works. In Donoghue v Stevenson[33] the Court of Appeal held that “liability was limited to physical damage caused by negligence and did not extend to economic loss” (Adriaanse, 2016, p.277). A leading issue in many cases, and what is of concern is the recuperation of costs associated with building repairs due to negligently constructed works. To ensure issues such as these do not arise, the contract terms regarding liability need to be clearly assessed and redefined, as to not leave construction professionals wholly responsible.
2.3.6.1 Design Culpability in the Law of Contract and Tort
Carl J Circo (2005) advocates that contract principles have been proven to be, “less significant than tort principles in the development of design liability law” (p.599). He went on to say that very few construction contracts fully prescribe, “standards of professional responsibility” with few implementing the standard of care present in the law of tort. It is often declined in court that an implied contractual obligation to produce a design without defects and with a certified result exists.
However, in contrast, and held in Prier v Refrigeration Engineering Company[34], under a D&B contract, “where a person holds himself out as qualified to furnish and does furnish, specifications and plans for a construction project, he thereby impliedly warrants their sufficiency for the purpose in view”. This could infer its applicability only to design and build contracts, however, it is ambiguous. Design culpability in the law of tort is subject to reasonable skill and care, regardless of the designer’s profession. In contract, it is only when the purpose for the works they are designing is known, that the consultancy’s designer’s responsibility evolves from the exercise of reasonable care and skill, into a strict liability.
2.4 Construction Contracts
The purpose for organisations involved in a construction project to enter into a contract is to set out the rights, duties, and obligations of each party, primarily for clarity and to, “record their expectations” (Victor O. Schinnerer and Company Inc., 2017, p.2). Further to this, McDonnell (2013) stated that contracts establish, “the design professional’s terms and scope of service” (p.659). He suggested that clear contractual provisions will:
- “Preserve parties’ risk allocation;
- enforce the reasonable expectations of the parties;
- place the risk of loss on the party better able to bear it, and
- cement the contractual foundation of the design industry with certainty and predictability” (p.671-672).
Despite forming this contractual relationship, McKeeman and Rossetti (2007) conflict McDonnell’s remarks by suggesting that, “design professionals would not be able to contractually limit their potential liability on a project” (p.10). Revealing that protection could be achieved through, “broader and/or more stringent contractual protections” (p.10). Professor Sarah Lupton (2015) recognises that “all too often, perhaps because of a shortage of time, insufficient care is given to finalising these key documents” (p.96).
2.4.1 The Joint Contract Tribunal 2016
The JCT suite of contracts is the most frequently used, accounting for 39% of the UK market in 2015 (Waterhouse et al., 2015, p.17), used predominantly for lower value projects. However, the National Construction Contracts and Law Survey 2015 highlighted the shift in commonly used contracts, with a decrease in the use of JCT forms, accounting for 60% in 2011 (Waterhouse et al., 2015, p.17). Drafted by a cross-section of industry bodies, the JCT suite is generally acknowledged as having a pro-contractor bias. The suite of contracts includes minor works, intermediate, standard, design and build, and ‘with contractor’s design’ options.
2.4.2 NEC Engineering and Construction Contract 2013
The NEC suite of contracts has seen a rise in use accounting for 30% of the UK market in 2015 (Waterhouse et al., 2015, p17), commonly used for higher value projects. In 2011, only 16% of people said they used NEC contracts most often (Waterhouse et al., 2015, p.17). The Office of Government Commerce endorses NEC contracts as ‘Achieving Excellence in Construction’, a set of government principles around collaboration and whole life cycle costing for construction procurement (Office of Government and Commerce, 2007). Unlike JCT though, its contract forms are a ‘one size fits all’ approach, with options to tailor to the project.
2.4.3 Traditional Procurement
Sir Michael Latham’s (1994) Constructing the Team report commented on the segregation between the design and construction phases on a project, and also the lack of clarity between the duty to use reasonable skill and care and the requirement of fitness for purpose. Traditional building procurement divides design and construction into two separate entities, “the employer and the professional designers assume responsibility for the design of the building, and the contractor agrees to build what has been designed” (Adriaanse, 2016, p.128).
The employer’s design team should produce full drawings, specifications and a bill of quantities, to enable the contractor to construct. The contractor has an obligation to construct, “in strict accordance with the contract documents provided” (Hughes et al., 2015, p.197). It is important to establish whether a defect is because of the design or construction phase of works, as this identifies who is culpable for it. Taking into account this segregation, “the employer when faced with a defective building or structure may have to bring claims against both the designer and contractor” (Adriaanse, 2016, p.304). Commonly defects do not fall entirely into either category of design or workmanship, which leads to an overlap between the two.
2.4.4 Contractor’s Designed Portions (CDP)
Under a traditional form of contract, the contractor will be culpable for elements of ‘contractor’s design’. The employer must notify, as a requirement of the contract, the contractor of all work that is to be a CDP. The importance of this was highlighted in Walter Lilly & Co Ltd v Mackay[35], where it was held that the contractor was not liable for defective work, as a clear notification was not given for the CDP packages of work. “Subsequent instructions issued in conformity with the contractual terms” (Lupton, 2015, p.99) were required. However, Circo (2005) questioned whether notifications involving additional design require control to, “prevent the lead design team from requiring unwarranted, unreasonable, or excessive changes to the specialty design” (p.599).
If it is intended that the contractor is to take on such responsibility, it should be made, “certain that the contract documents clearly identify the scope of services and functions that each design party will provide” (Circo, 2006, p.599). Further to this, the documents must identify suitable procedures for, “submitting and finalising the specialty design documents” (p.599). Circo (2006) went on to highlight, “points of connections and interfaces” as, “important design parameters that the lead design team must furnish” (p.599). Where the works comprise Contractor’s Designed Portions, the contractor is obliged to complete the design, “including the selection of any specifications for the kinds and standards of the materials, goods and workmanship to be used in the CDP Works” and integrate the design, “with the design on the Works as whole” (The Joint Contracts Tribunal, 2016, p.35).
Work on these design packages cannot proceed until they have been signed off by the design team. Adriaanse (2016) questioned, “to what extent can the contractor depend on the design provided by the employer’s professional advisers?” (p.309). In Cooperative Insurance Society Ltd v Henry Boot (Scotland) Ltd (Costs)[36], the contractor argued that they were only responsible for generating detailed drawings from the initial design produced by the employer, without liability to check its feasibility. It was held, the conditions of the contract, “required the contractor to develop the conceptual design provided by the engineers into a design capable of construction” (Adriaanse, 2016, p.309). Therefore, the contractor was required and responsible to form an opinion as to whether he believed the design was valid at the point in which he took it on. However, subject to clause 2.13.2 (under the SBC/Q Standard Building Contract With Quantities 2016) it now states, “the Contractor shall not be responsible for the contents of the Employer’s Requirements or for verifying the adequacy of any design contained within them” (The Joint Contracts Tribunal, 2016, p.36).
This is a significant contractual provision from a contractor’s perspective as it rebuts the decision held in Cooperative (2002), where the contractor was liable for the complete design. Although ultimate responsibility to ensure the design complies with the contract still rests with the contractor. It is important that the preliminary design that is handed over to the contractor is produced with reasonable skill and care, as highlighted by John Mowlem & Co v British Insulated Callenders Pension Trusts Ltd and Others[37].
Proceedings took place to identify whether the contractor was liable for defective works. It was held that the engineers were guilty due to their negligent design, which ultimately resulted in failure. Express terms under the NEC Engineering and Construction Contract 2013 for the contractor’s design liability is written in Section 2, under clause 21.1, “the Contractor designs the parts of the works which the Works information states he is to design” (Institution of Civil Engineers, 2013, p.7). The acceptance procedure for contractor’s design is under clause 21.2 and 21.3. The contractor is required to submit, “the particulars of his design… to the Project Manager for acceptance” (Institution of Civil Engineers, 2013, p.7). As with the JCT contracts, these sections of works cannot proceed until the design has been accepted. Clause 21.3, states that the design may be submitted in parts if, “parts can be assessed fully” (Institution of Civil Engineers, 2013, p.7).
Further to this, the project manager has the authority to reject the design where it does not comply with the Works Information. As highlighted by McElroy, Friedlander and Hennig Rowe (2006) the role of the architect/ engineer (design team) has reformed with regards to the review and approval of drawings. “Design professionals now seek to limit their liability for design detail provided by others to a review for overall compliance with the design intent” (p.10). This could be seen to be an area of controversy regarding industry practice. The National Construction Contracts and Law Survey (2015), concurs with these statements, accounting Contractor’s Designed Portions for 17% of disputes in construction projects due to the grey area surrounding liability for these ‘packages’, their extent and approval (Waterhouse et al., 2015, p.23).
However, the conclusions drawn from Pain and Bennett’s (1988) study found that the 49 projects they surveyed using JCT with Contractor’s Design (many of whom were using it for the first time) experienced no serious issues, with a fraction suffering minor difficulties, which suggests that these packages have become more of a problem in recent years.
2.4.4.1 Employer’s Requirements
The Employer’s Requirements (ER) is a list of necessities formed by the design team for each CDP ‘specialist package’ documenting what the contractor is required to achieve. They are set out in the tender contract documents and in response to them, the contractor will submit Contractor’s Proposals. Chan, Chan, and Yu (2005) believe the clearer the ER, the fewer problems the contractor will encounter during the construction phase of works. The level of detail included in the requirements and the extent of the design handed over to the contractor is variable from project to project.
Chan and Yu (2005) note that the amount of information provided by the consultants is a common area of dispute as it may be a simplistic specification; however, it may also be a complete performance specification and concept design (Pain and Bennett, 1988). McElroy et al. (2006) stated that often the construction phase of works commences prior to the completion of, “plans and specifications” (p.4) which are likely to have a critical effect on the “timely completion of the design phase” (p.8). Ultimately, if the ER is clearly defined from the outset it can pave the way for project success. “The better prepared they are, the keener the price from the contractor and the less likely there will be disputes” (Institution of Civil Engineers, 2016).
2.4.4.2 Sub-Contracting
It is the main contractor’s responsibility to procure specialist subcontractors for any contractor’s design however, the employer or design team may propose their preferences. Often the contractor will tender out to three or four companies and present a list to the design team to decide who is appointed to carry out the work. This is a domestic subcontract, whereby the contractor is liable as if he had not subcontracted.
Further to this, the employer or design team can instead put forward a list of three or four subcontractors whom they wish the contractor to work with. The liability for these named subcontractors remains with the contractor as they have a choice. It is only when the employer or design team nominates a subcontractor, which the contractor is required to use without any choice, that the liability for that subcontractor is shifted back onto the employer or design team.
Experience in industry highlighted that there are design professionals with an in-depth understanding of this liability clause, which results in a manipulative approach. Albeit the design team named subcontractors, a forceful encouragement of one left the contractor with no choice but to go into contract with them. The design team was then able to escape liability, which would have been imposed had the subcontractor been nominated, although ultimately, they made the choice.
2.4.5 Design and Build Procurement
Design and build contracts involve, more often than not (Turina, Radujkovic, and Car-Pusic, 2008), the contractor taking on sole responsibility for both design and construction of the works (Doloi, 2008). Rowlinson (1987) considers the approach to be independent, suggesting expertise for both phases should reside with a single stakeholder who has, “sufficient resources to complete any task that arises” (p.3). Castro (2009) proclaimed that the contractor, “must be held responsible for the hybrid responsibilities they have assumed” (p.30).
Miller (1982) argues that “the design-build model removes the internal conflict, waste, and clouding of responsibility that is inherent between the client, architect and contractor” (p.128). Further to this, Turina et al. (2008) suggest that this procurement route reduces the likelihood of misunderstandings and simplifies processes and Tam (2000) notes it, “improves buildability” (p.2). However, Castro’s (2009) counteracting views consider the process to have, “inherent conflict” due to, “the merger of these opposing roles” (p.31).
2.5 Chapter Summary
In expectation of a greater understanding of current thinking on design culpability in construction contracts, the review appraised literature surrounding the research area. When dealing with design liability, Hughes et al. suggest considerations that need to be taken into account: “the nature of design and its complexity, how the law actually defines design obligations; and third, which participants in the construction process may be liable in respect of design faults” (Hughes et al., 2015, p.197). Delineation of design culpability within construction contracts can often be the root cause of disputes that are detrimental to project team relationships. The National Construction Contracts and Law Survey (2015) found that contractor’s designed portions accounted for 17% of disputes in construction projects due to the grey area surrounding liability for these ‘packages’.
There is often confusion about the extent of CDPs, unclear or overlapping requirements appearing in contractual terms, and their related technical documents. Gaafar and Perry highlighted the confusing nature of the standard of care applicable to construction contracts, stating that, “reasonable skill and care may equate to a fitness for purpose” (Gaafar and Perry, 1999, p.306) obligation, dependent on the specific wording of the clause. It is vital that the contracting parties define what is intended within the contract documents. In particular, the hierarchy of contract clauses within each document, and the relationship between documents, and should ensure that the allocation of detailed design tasks and level of responsibility for each is crystal clear, with no gaps or overlaps (Waterhouse et al., 2015).
Table 2.1: Design culpability in construction contracts (Subject to standard clause provisions)
Where contractor’s designed portions are integrated within projects, the following may benefit their clarity:
- The extent of the package should be accurately defined;
- Special care should be given to the interfaces between CDP and non-CDP items, and
- It may be that at tender stage, the exact scope of items of work that are to be the contractor’s design is unknown. Where this occurs, procedures for the instruction of CDP items need to be distinctly noted in the contract terms and obeyed to ensure there is no doubt an item of work is or is not a CDP.
Further research questions that have arisen from the literature review are as follows:
- How can standard contracts be reviewed and updated to include interfaces for CDP packages, specifically to identify design responsibility at these boundaries or outline an agreement going forward on how to manage interface CDP elements with the remaining design;
- Understand how the standard of care be clearly defined within all construction contracts, to avoid confusion and dependency on specific contract clause wording, and
- Achieve an understanding as to how contractors can contractually approach design liability, to manage risk, avoid disputes, and understand their obligations.
3.0 Methodology
3.1 Introduction
This chapter explores and compares research approaches, and identifies the most suitable. A decisive explanation has been given regarding the choice made, and potential limitations and restriction for the research have been acknowledged.
3.2 Narrowing Down the Research Topic
Research can be defined as, “a scientific and systematic search for pertinent information on a specific topic” (Kothari, 2004, p.1). It is, therefore, critical that a process of selection, narrowing down and framing of the final focus of the research takes place at this stage of the research project (See Figure 3.1). Following an industrial placement, the identification of design culpability as an initial idea led on to discussions with industry professionals (colleagues) along with academic staff, and a review of scholarly journals; which produced a refined topic area.
Focus areas assisted in producing a preliminary report on Contractor’s Designed Portions from both an employers and contractor’s perspective. The evolution from the initial idea to an appraisal of the effectiveness of current contract provisions and legislation to restrict unclear delineation of design culpability led to a solution and aim to provide a framework to determine the level of design culpability applicable to construction contracts and produce guidance on understanding design responsibility.
Figure 3.1: The narrowing down of the research topic (Naoum, 2013, p.11)
3.3 Research Classification and Strategy Approaches
Research is conducted to find out the result of a given problem. It can be described as an “action plan” (Naoum, 2013, p.39) for obtaining and analysing data. According to Fraenkel and Wallen (1993), the term research can refer to any sort of, “careful, patient study and investigation in some field of knowledge, undertaken to discover or establish facts and principles” (p.4). Kerlinger (1979) presents a more detailed definition of research defining research as a “systematic, controlled, empirical, and critical investigation of hypothetical propositions about the presumed relations among neutral phenomena” (p.8).
In contrast to these definitions, Fellows and Liu (2015) illustrated research as a “voyage of discovery” (p.4). The purpose of research is to, “gain familiarity with a phenomenon or to achieve new insights into it” (Kothari, 2004, p.2). Research methodology is, “the principles of the methods by which research can be carried out” (Fellows and Liu, 2015, p.49) with aims to implement a precise and analytical approach. There are various approaches to data collection, however, researchers suggest that two main paradigms have influenced research, both quantitative and qualitative.
3.3.1 Quantitative Research
Quantitative research is, “objective in nature” (Naoum, 2013, p.39) and tends, “to relate to positivism” (Fellows and Liu, 2015, p.29). Amaratunga, Baldry, Sarshar and Newton (2002) suggest that it is, “concerned with determining the truth-value” of suggestions to test a theory (p.22). This correlates with Johnson and Onwuegbuzie’s (2004) statements that major characteristics of quantitative research include, “theory or hypothesis testing” (p.18). This research approach is deductive in nature, subject to the researcher’s point of view.
By revealing hard, reliable data that is tangible it allows for, “flexibility in the treatment of the data” (Amaratunga et al., 2002, p.22) to enable verification of reliability. This research strategy is superlative, “when you want to find facts about a concept, a question or an attribute” (Naoum, 2013, p.40). The approach enables the researcher to study the “relationship between the facts in order to test a particular theory” (Naoum, 2013, p.40). The usual process for quantitative research originates with the researcher’s theory. A set of data is collected to test this theory, which can be analysed to evaluate whether there is ‘truth’ behind it.
3.3.2 Qualitative Research
Qualitative research seeks to, “gain insights” (Fellows and Liu, 2015, p.29) through investigating, “the beliefs, understandings, opinions and views” (p.29) of people. The role of the researcher when conducting qualitative research is to gather a, “holistic overview of the context under study” (Punch, 2013, p.119). It focuses on words and is, “subjective in nature” (Naoum, 2013, p.41). Typically presenting the point of view of the participants this strategy, “emphasises meanings, experiences and description” (Naoum, 2013, p.41). It can be further broken down into two types of research, exploratory and attitudinal. Unlike quantitative research which tests a theory, qualitative is an inductive method, whereby the theory is emergent.
Exploratory research is used when there is a restricted amount of knowledge surrounding your topic area, it aims to highlight and generate, “a clear and precise statement of the recognised problem” (Naoum, 2013, p.42). Attitudinal research, “is used to subjectively evaluate the opinion, view or the perception of a person, towards a particular object” (Naoum, 2013, p.43). This method can often be time-consuming; it refers to the respondents' perception in their professional discipline and relies on the subjective interpretations of the researcher.
3.3.3 Quantitative vs. Qualitative Research
Amaratunga et al. (2002) suggest that there are no ideal solutions, each approach involves, “a series of compromises” (p.20) complimenting John Creswell’s (2013) thoughts, “that all methods have bias and weaknesses” (p.14). Though Johnson and Onwuegbuzie (2004) state that purists for each paradigm believe their approach is the most valuable for research and that the strategies, “should not be mixed” (p.14). However Onwuegbuzie and Leech (2005) contest this theory, suggesting that reliance on only, “one type of data is extremely limiting” (p.384)
Triangulation, as the third research paradigm, could be seen to bridge the division between these two alternate approaches, by incorporating each of their strengths. Johnson and Onwuegbuzie (2004) state, “the bottom line is that research approaches should be mixed in ways that offer the best opportunities for answering important research questions” (p.16). Naoum (2013) identifies the main features of both a questionnaire survey and an interview, highlighting their strengths and weaknesses (see Table 3.1).
Table 3.1: Comparison between a postal survey and interview technique (adapted from Naoum, 2013, p.60)
3.3.4 Triangulated Research
Johnson and Onwuegbuzie (2004) depict triangulation as, “an expansive and creative form of research” (p.17). This mixed-method approach allows the researcher to, “reduce or eliminate disadvantages of each individual approach while gaining the advantages of each, and of the combination” (Fellows and Liu, 2015, p.29). This allows for a “multi-dimensional view of the subject, gained through synergy” (p.29).
Triangulation seeks to enrich the results and heighten the validity. Rossman and Wilson (1991) (cited in Amaratunga et al. 2002) discuss the benefits of combining both quantitative and qualitative research methods, suggesting it is, “to elaborate or develop analysis; providing richer details; to initiate new lines of thinking” (p.23). However, problems can occur when analysing the data if the findings contradict one another – which dataset has superiority?
Tashakkori and Teddlie (cited by Johnson and Turner, 2002) presented the “fundamental principle of mixed methods research” (p.299), whereby methods should strategically combine paradigms in a certain way to ensure complementary strengths are produced without any overlapping weaknesses.
3.3.5 Research Design
Research design concerns the way in which the researcher links their data collection to the research question; in order draw conclusions from it. Reliability and validity refer to, “the degree to which a researcher draws accurate conclusions” (Fellows and Liu, 2015, p.92) to reduce the possibility of inaccurate data. Precautions were therefore undertaken when planning the survey and interview questions, to remain unbiased. Triangulating the data sources allowed for, “convergence across qualitative and quantitative methods” (Creswell, 2013, p.15) to provide a means of examining the accuracy of the paradigms against one another.
The convergent parallel mixed methods model involves the researcher merging the data sets, “to provide a comprehensive analysis of the research problem” (p.15). Data is collected concurrently, and the findings are integrated into the analysis and conclusions, where incongruent results can be clarified. Fellows and Liu (2015) suggest that conclusions that concern both, “breadth and depth” (p.113), will have maximum validity. Figure 3.2 illustrates how the results from different data sources converge, to achieve breadth and depth.
Figure 3.2: Triangulation of Qualitative Data (Fellows and Liu, cited in Amaratunga et al., 2002, p.24)
3.4 Adopted Data Collection Methods and Justification
To achieve the aim, and meet the objectives (as illustrated in Figure 3.3), a triangulated data collection approach was determined to ensure valid data was obtained. Johnson and Turner (2002) recognise that each method of collection has limitations along with strengths and Tashakkori and Teddlie propose that their “fundamental principle of mixed methods research” (cited by Johnson and Turner, 2002) is followed for the subsequent reasons:
- “To obtain convergence or corroboration of findings;
- To eliminate or minimise key plausible alternative explanations for conclusions drawn from the research data, and
- To elucidate the divergent aspects of a phenomenon” (p.299).
Triangulation is able to achieve a much wider appraisal of the research data with greater depth as the researcher can ask a, “broader and more complete range of research questions because the researcher is not confined to a single method or approach” (Onwuegbuzie and Leech, 2005, p.21). Ultimately the investigator, “can provide stronger evidence for a conclusion through convergence and corroboration of findings” (p.21).
The mixed method approach will aid in formulating more in depth insights and conclusions, which may have been overlooked had there only been a single method used. Bazeley (cited in Ahmed, Opoku and Aziz, 2016) argues that mixed-method data compliments one another, “to offer a more comprehensive picture for the study” (p.40).
Figure 3.3: Illustration of Data Collection Methods to achieve the formulated objective
3.4.1 Questionnaires
Questionnaires are a data–gathering instrument, filled out by research participants. They are widely used to, “find out facts, opinions and views on what is happening” (Naoum, 2013, p.52). Naoum (2013) suggests that the three main advantages of questionnaires are economy, speed and consultation (p.52). Generally the bulk of responses will be, “received within 2 weeks” (Naoum, 2013, p.52), but a further couple of weeks needs to be allocated for follow-ups
Questionnaires allow the participants to spend time consulting documents and potentially discussing with co-workers before finalising their answers, a luxury that is not offered when undertaking interviews, where answers must be given on the spot. Tashakkori and Teddlie (2002) suggest that when composing a questionnaire, “it is important to follow the 13 principles of questionnaire construction” (p.303) illustrated in Table 3.2. If the questions asked are well designed and precise the results produced should be, “valid and meaningful” (Mathers, Fox and Hunn, 2010, p.19), the questions must be, “self-contained and self-explanatory” (p.31).
Questionnaires are widely recognised as far more expedient than interviews, providing anonymity, which is likely to produce greater honesty. The length of the survey needs to be sensibly considered as the common nature leads to a concise amount of questions, which may overlook elements of required data.
Table 3.2: Principles of Questionnaire Construction (adapted from Tashakkori and Teddlie, 2002, p.303)
3.4.1.1 Formulating the Questionnaires
Gaps highlighted following the literature review prompted the focus points within the questions’ scope. Naoum (2013) identifies three significant phases which need to be considered when formulating a questionnaire:
- “Identifying the first thought questions;
- Formulating the final questionnaire, and
- Wording of questions” (p.64).
First thought questions are based on the literature review, they should not be arbitrary. By ensuring the research has been narrowed down to a specific focus area (section 3.2) it should help, “to formulate the final questionnaire more easily” (Naoum, 2013, p.64). Naoum (2013) suggests that following the initial identification of questions, “sections” (p.64) should be introduced to contain and organise the structure and list of questions. It is beneficial that these sections, “correspond” (p.64) with the objectives.
Finally, upon determining the scope of the questions, the wording needs to be analysed to avoid ambiguity and leading questions. A quantitative questionnaire was implemented which is a, “completely structured and closed-ended questionnaire” (Tashakkori and Teddlie, 2002, p.304) whereby, “all of the questions provide the possible responses from which the participant must select” (p.304).
However, there was an anomaly to this standard form as a single question was mixed. This allowed the participants to respond in their own words with an, “other (please specify)” category, if they believed the responses provided needed further explanation. A section of the questionnaire was a, “summated rating scale” (Tashakkori and Teddlie, 2002, p.304), a likert-scale. Likert-type or frequency scales use a fixed choice response format and they are designed to measure attitudes or opinions (Bowling, 1997; Burns, & Grove, 1997).
They consist of, “attitudinal statements on the survey object” (Naoum, 2013, p.74), which gives the respondent the opportunity to express their, “degree of agreement or disagreement on a particular scale” (p.72). The mode of distribution selected was an Internet based questionnaire. This provided both cost and time benefits, with secondary benefits for data analysis. The online instrument used was ‘Survey Monkey’, an easy to use survey builder that produced real time results. The data collected is generated and presented in statistical packages, readily available for analysis. “For online surveys in which there is no prior relationship with recipients, a response rate of between 20-30% is considered to be highly successful” (Surveymonkey.co.uk, 2017).
Following the sample selection, a covering email was issued to potential respondents, with the hyperlink attached, along with an introduction that clarified the context of the questionnaire. As suggested by Naoum (2013) (in section 3.4.1) a two-week period was stipulated for responses, with a follow up email issued after one week.
3.4.1.2 Pilot Study
Fellows and Liu (2015, p.97) suggest it would be pragmatic to carry out a pilot test prior to administering the questionnaire to the selected sample. This corresponds with Tashakkori and Teddlie’s (2002) Principle 13 (see Table 3.2), which states that the researcher should always pilot-test their questionnaire. Mathers et al. (2010) advise that where a questionnaire is designed for self-completion, a pilot-test has many beneficial advantages, “as nobody will be around to clear up misunderstandings” (p.30). Through enlisting current final year colleagues undertaking Architectural Engineering and Design Management, an assessment of clarity, prime length and ease of response was considered to refine and improve the content. Along with these students, the project supervisor Wayne Lord enlisted his expertise to further advance the flow of the questionnaire.
3.4.1.3 Sample Selection
Naoum (2013) depicts two key criteria that need to be considered when selecting your sample; “what do you want to know and about whom do you want to know it” (p.58). Following the findings from the literature review, having identified the grey areas within the current legislation, it was recognised that the most applicable sample to select for the data collection would be industry professionals, currently working for a tier one UK contractor. This would provide an understanding of their current prospective with regards to design culpability, ultimately producing a greater chance of valid and reliable data.
The contractor chosen predominantly procures traditional contracts with design portions, specifically selected as they continuously face difficulties due to the scope of their design responsibility. Despite the possible accusation of the contractor being a convenient sample due to previous employment, the contractor was carefully considered regarding their approach to procurement and the issues they faced.
3.4.1.4 Limitation of Questionnaires
Questionnaires are dependent upon the selected sample, and therefore the validity and reliability of the results relies upon the participants that have taken part. Participant’s views may be distorted in an attempt to portray themselves (or even their company) in a positive light, “social desirability” (Fellows and Liu, 2015, p.96) bias. To reduce social pressure, certifying that the survey is anonymous, could contribute to the reduction of this bias.
Likert-scale scales are subject to limitations due to several causes. 5-point scales (or any odd numbered scale) give the respondents the opportunity to, “opt-out of answering a question by selecting the mid-point” (Fellows and Liu, 2015, p.172); said to be, “sitting on the fence” (p.172). This gives rise to suggestions to implement an even number of response points, to eliminate the possibility with, “no central point” (p.172). However, this may be forcing a participant that has no opinion to have one.
Further to this, there is said to be an avoidance of selecting the, “strong” response points creating a, “central tendency” (Naoum, 2013, p.98) bias. “Acquiescence” (Fellows and Liu, 2015, p.184) bias is another limitation of likert-scales, whereby the respondents tend to agree with the statements as presented. Non-respondents from the selected sample may represent an area of data that has been overlooked, differing from what has been received, jeopardising the validity. The inability to gain a deeper insight into the participant’s responses further refutes the data’s richness. Naoum (2013) suggests that, “some of the limitations of the questionnaire can be overcome by supplementing it with personal interviews” (p.54), thus triangulation of the data collection was selected.
3.4.1.5 Analysis of Questionnaire Results
The questionnaire was sent to 155 industry professionals (working for a UK Contractor). Out of these 155, 46 replied, therefore a response rate of 30% was achieved (highlighted in section 3.4.1.1 as a highly successful rate). The data collected was transferred to Excel, coded and statistically analysed using SPSS (Statistical Package for the Social Science) (Ibm.com, 2017), refer to Appendix G. Both descriptive and inferential statistics were used to analyse the quantitative data. Cross tabulation depicted the frequency distribution of the variables, and a two-tailed Independent T-Test defined the mean and standard deviation. Further to this, the Pearson’s Coefficient of Correlation established statistical relationships.
3.4.2 Interviews
Bryman (cited in Ahmed et al., 2016) stated that interviews, “are a major data-collection technique commonly used to elicit data” (p.43), defined by Sheppard (cited in Ahmed et al., 2016) as a, “conversation with a purpose” (p.43). Tashakkori and Teddlie (2002) go on to say that the interviewer needs to initially establish rapport, prior to asking the interviewee a series of questions. Interviews permit, “social interaction and free flow of communication” (Ahmed et al., 2016, p.43). The interviewer is required to remain impartial to the interviewee’s responses to, “reduce the potentially biasing effect of the interviewer” (Tashakkori and Teddlie, 2002, p.305). However, this does not mean that the interviewer cannot ask for clarity if further detail is required. Telephone interviews were utilised to test the validity of the questionnaire, as well as gain further insight into the participant’s views and responses to the survey.
3.4.2.1 Formulating the Telephone Interviews
Interviews are often said to be the, “best way of achieving high quality data” (Mathers et al., 2010, p.8) habitually, “collecting more complex information” (p.8). Naoum (2013) advised that interviews, “can take three forms: unstructured, structured and semi-structured” (p.55), the principles for each are identified in table 3.3. Fellows and Liu (2015) suggest that the major differences of these three forms, “lie in the constraints placed on the respondent and the interviewer” (p.159).
Table 3.3: Interview Types (adapted from Naoum, 2013, p.55 & 56)
Unstructured interviews do not contain a rigid structure, they are, “without predetermined questions” (Wiesner and Cronshaw, 1988, p.279). Structured interviews cover a fixed set of questions often with, “predetermined answers” (p.279). Semi-structured interviews predominantly identify, “key topics” (Naoum, 2013, p.55 & 56) with scope to elaborate. Telephone interviews are useful if the respondents are, “widely geographically distributed” (Mathers et al., 2010, p.9).
It is suggested that once the interviewee has committed to taking part, they are less likely to withdraw therefore, “the response rate is relatively high” (Naoum, 2013, p.57). The design of the interviews followed an unstructured approach, with focus on a general topic, ‘whether they had any further comments regarding design liability in construction contracts or suggestions as to how design liability can be better outlined within a construction contract, to manage risk’, to enhance validity exclusive of restraints.
3.4.2.2 Sample Selection
The questionnaire provided the respondents with an opportunity to leave their contact details if they wanted to participant in a further telephone interview, to provide depth to the results found in the questionnaire. 10 respondents agreed to participate, which led on to telephone interviews with these industry professionals, of varied commercial experience, working for a contractor. All participants remained anonymous for confidentiality.
3.4.2.3 Limitation of Interviews
Interviews are susceptible to interviewer bias due to their flexibility (Naoum, 2013). The non-verbal communication and the way the interviewee acts or reacts may, “mislead the interviewer to incorrect judgement” (p.60). Planning interviews is time consuming, and the small sample of participants portrays a limited view, which may not be representative of industries perceptions.
3.4.2.4 Analysis of Interview Results
Analysis of results entailed identification of themes to highlight patterns, correlations and disparities. To enable thorough analysis, the interviews were recorded and transcribed. To ensure the conclusions were reliable the findings from the literature review, questionnaire and interviews were collated.
3.5 Limitations of Research
Fellows and Liu (2015) depict how important it is when undertaking research, “to be demonstrably aware of the limitations” (p.28). They suggest that the following impact upon validity and applicability of the conclusions drawn:
- “Sampling methods of collecting data;
- Techniques of analysis;
- Time restrictions;
- Cost restrictions, and
- Resource availability” (p.39).
To overcome these limitations, the data collection methods were triangulated to aid in bridging the gaps, thus ensuring the validity of the consequential research and results. Additional benefits of this mixed-method reduce the time spent on gathering data, as well as cost, due to the smaller sample of interviews and larger sample selection for the questionnaire. Resource availability was confined to reliable and valid sources; professional journals, research reports, poignant case law, and relevant books.
A further limitation of the research concerns the individual researcher, which is likely to cause subjective bias, potentially impacting or distorting the data (Ahmed et al., 2016). Following the receipt of the questionnaire responses, 10 participants were contacted to report on a more in-depth understanding of their knowledge and views and discuss any queries. This step served to eliminate any bias in the results that may have developed due to different interpretations of the questions asked (Ahmed et al., 2016).
3.6 Ethical Considerations
As highlighted by Fellows and Liu (2015) research ethics refers to, “the moral principles guiding research” (p.247). Guidelines were adhered to throughout the study to ensure the researcher maintained ethical principles and standards. Permission for the study was granted through the Civil and Building Engineering School of Loughborough University. Informed consent, confidentiality of information and anonymity of the participants was guaranteed. Further to this, it was understood that research participants must voluntarily participate.
3.7 Chapter Summary
An in-depth review of the available research and data collection methods was undertaken to ensure the most appropriate method was implemented, thus reducing the limitations of the research, contributing towards valid and reliable results with breadth and depth.
4.0 Data Collection and Analysis of Results
4.1 Introduction
In conjunction with the aim and objectives of the project, this chapter reviews the data collected to present the research findings. The results from both the questionnaire survey and telephone interviews are gathered and collated, and further analysed and cross-referenced to provide a valid, overarching view of industries perspectives.
4.2 Analysis of Questionnaire Survey
4.2.1 Introduction
To accurately analyse the questionnaire results, three sub-themes were identified in line with the research aims and objectives:
- Classifying culpability;
- The importance of managing design, and
- Prominent issues during the construction phase of works.
The participant’s responses have been arranged thematically, within these sub-themes, to purposefully analyse the data. The sample size was moderately small (n=46) therefore both numbers and percentages have been identified. To ascertain the mean value for the questions, a two-tailed independent t-test was carried out using SPSS (Statistical Package for the Social Science) (International Business Machines (IBM) 2017), to determine differences in the participant’s opinions. Alongside this, correlations were documented to determine the relationship between industry experience, job role, and their opinions. Ordinal scale response coding aided statistical analysis of the data (see Table 4.1).
Table 4.1: Ordinal Scale Response Coding
4.2.2 Profile of Survey Participants
The demographic profile of the participants (see Table 4.2) reflects the breadth and depth of the study, providing both validity and reliability of the results. Of the 46 participants that took part in the survey, 30% were Design Managers, 20% were Project Managers, 15% were Commercial Managers, 13% were Quantity Surveyors, 9% were Legal Professionals, 7% were Directors, 4% were Site Managers and 2% were ‘Others’ (Estimator). Those that had over 15 years’ experience equated to 50% of respondents and those with less than 5 years’ experience in industry accounted for 33%. Those that fell in-between were equitably and evenly distributed.
Table 4.2: Demographic Profile of Survey Participants
4.2.3 Classifying Culpability
Classifying design culpability associated with construction contracts and the construction process was investigated with the following prompts:
- Perceptions of the standards of care (Q13);
- Awareness of D&B liability (Q15);
- Determining industries understanding of D&B liability (Q4);
- Effectiveness of CDP contractual provisions (Q5), and
- Compliance with contractual provisions (Q9).
Literature presented two distinct levels of design liability, of which the respondents indicated which they believed to be the stricter provision (Q13). The majority, 59% (27/46), understood that a ‘guarantee that the design will be fit for its intended purpose’ is the stricter of the two, albeit a very even outcome. This supports Gaafar and Perry’s (1999) findings that design liability is not well understood by the project participants. Further to this, a positive correlation (0.814) was reported, which linked industry experience with in-depth knowledge and accurate understanding of the levels.
The questionnaire sought to identify to what extent of design liability should a D&B contractor be responsible (Q15). An obligation to use reasonable skill and care accounted for 67% (n=31) of participants votes. There is, however, the potential for bias in the response, as the participants work for a contractor and thus would clearly prefer to limit their design liability. Conversely, the remaining 33% (n=15) of respondents selecting the stricter liability corresponds to the findings in Q13, where a lack of understanding the difference was highlighted. Participants indicated whether the inherent conflict in design and build contracts related to the dual role of the contractor (Q4). 46% (Strongly Agree, 7% n=3, Agree 39% n=18) of respondents agreed that there was a positive correlation which endorses Castro’s (2009) suggestions that conflict is caused due to the merging of the opposing roles.
The conflicting views identified in literature were further supported by the 37% (Disagree, 35% n=16, Strongly Disagree, 2% n=1) who disagreed with the statement. Agreeing with both Miller’s (1982) and Turina et al.’s (2008) studies advocating that D&B procurement is less conflicting due to the single point of responsibility. The survey highlighted a positive correlation (0.704) that design managers are more likely to affirm that CDP’s have grey areas as to the extent of their liability compared with other industry professionals (Q5). A reason could link to design manager’s close relation to managing the packages, therefore they consequently encounter the resultant issues.
Responses were narrowly varied (mean=1.78, SD=0.70) with a significant proportion of participants (33/46: Strongly Agree; 26% n=12, Agree; 46% n=21) agreeing that CDPs involve ambiguous grey areas. Thus, the interfaces necessitate identification and clarification which authorises Circo’s (2006) findings. Q9 sought to classify the efficacy of current legislation and contractual provisions, regarding liability avoidance. A focus on the misuse of the subcontracting clause highlighted that a clear majority of respondents, 76% (Strongly Agree: 15%, n=7, Agree: 61%, n=28), perceived legislation as ineffective due to their agreement that the design team manipulates the provisions.
This corresponds with studies undertaken by McKeeman and Rossetti (2007), who exemplify the requirement for broader and/or more stringent contractual protections to reduce the likelihood of misuse and confusion.
4.2.4 The Importance of Managing Design
The importance accurate design management has on the completion of a successful project was investigated with the following prompts:
- Effectiveness of a design coordinator (Q8);
- Appropriateness of interfaces between CDP/non-CDP (Q10);
- Compliance and acceptance of design requirements (Q11), and
- Perception of design management (Q14).
Respondents had conflicting views as to whether the design team were best placed to prepare and approve the design (Q8) (mean= 2.54; SD= 0.86), with 44% (n=20) agreeing, 33% (n=15) remaining neutral and 15% (n=7) disagreeing. McElroy et al. (2006) found that design professionals seek to limit their liability, not wanting to review and approve drawings.
These conflicting views suggest no professional is best placed, it is likely to be dependent on the nature of the specific contract, notwithstanding whoever is selected needs to understand their liability. The literature review highlighted that special care should be given to the interfaces between CDP and non-CDP items (Q10) (Circo 2006). To evaluate the care taken when identifying and recording responsibility in the contract provisions for CDPs, participants provided their experience. Responses were alike (mean=1.41) and hardly varied (SD=0.54). A positive correlation (0.494) was found, as 71% (10/14) of design managers strongly agreed with the statement that further care needs to be taken
Comparison of averages indicated that design managers (n=14) had a higher perception of the difficulties present in the interfaces of the packages (mean=1.14) than those caused by grey areas (mean=1.29). The survey evaluated the samples opinion on the process of contractor’s design acceptance (Q11). A high proportion of participants, 72% (Strongly Agree, 33% n=15, Agree 39% n=18), established there was a correlation between a lengthier design process and a lack of acceptance of CDPs, supporting McElroy et al.’s (2006) findings.
Suggestions proposed by Circo (2006) identified the requirement for a schedule for submission, timing of any comments, approvals and other actions from the design team. It was further identified that experience in industry positively correlated (0.438) with those who agreed with the statement, which would link to a greater likelihood of these respondents encountering such issues. When asked whether design management and responsibility were of greater importance than other factors such as single point responsibility, cost certainty, constructability and shorter project duration (Q14), 76% (n=35) of participants agreed that these factors were of equal significance.
One respondent noted, “design management will have an impact on all of the others, for good or bad” another stated that “these factors all have varying degrees of importance depending on the client drivers, which could be cost, programme or quality”. To ensure design management is appropriately assumed, Circo (2006) recommended that refinements in contractual arrangements will be required to serve the interests of all parties and the industry, “which may give rise to variations on established project delivery systems” (p.637).
4.2.5 Prominent Issues During the Construction Phase of Work
To identify the participant’s perceptions of the key issues that arise during construction, the following prompts were used:
- Perception of disputes:
- Reducing the likelihood (Q3 & Q7), and
- Increasing the likelihood (Q6).
- Identification of severe issues (Q12)
Participants reflected on whether they felt that clear contractual provisions would reduce the likelihood of disputes (Q3). The majority agreed, 89% (Strongly Agree, 39% n=18, Agree, 50% n=23), which supported McKeeman and Rossetti’s (2007) views. Q7 required the respondent’s opinion on whether they believed single point responsibility to be less conflicting than split culpability. It was identified that 71% agreed, (Strongly Agree, 17% n=8, Agree, 54% n=25), in correspondence with Miler’s (1982) remarks.
Albeit countering Castro’s (2009) observations that were in line with the lesser proportion disagreeing. (7% n=3), with even three respondents strongly disagreeing (7%). Participants expressed views on CDPs, and whether they felt they are a common cause of disputes between parties (Q6). Conflicting views were recorded, however, a sizeable proportion agreed with the statement, 89% (Strongly Agree, 39% n=18, Agree, 50% n=23), with a mean value of 1.74 (SD=0.71). A positive correlation (0.836) was documented, those with greater experience in the industry agreed.
The findings suggest that CDPs are cause for disruption, which supports the National Construction Contracts and Law Survey findings, declaring CDPs a result of 17% of disputes in construction projects (Waterhouse et al. 2015). To identify the key issues believed to have the greatest effect on the construction phase of the project, regarding design culpability (Q12), the respondents acknowledged poor specification (61% n=28) as the leading challenge. The participants could select more than one option, therefore the percentage calculated exceeds 100%. As recorded in Figure 4.1 below, the participants indicated a multitude of issues.
Results support McElroy et al.’s (2006) findings on design approval, Circo’s (2006) acclamations on blurred lines of responsibility and poor specification and the Institute of Civil Engineers (2016) view on the preparedness of employer’s information.
Figure 4.1: Issues During the Construction Phase (Q12)
4.3 Analysis of Interviews
4.3.1 Introduction
Unstructured interviews were conducted to provide depth and validate the results found from the questionnaire survey. The interview transcripts are presented in Appendix H and the interviewee was posed with a single statement, to allow free flow of thought: Comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved.
Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations. To accurately analyse the telephone interview results, five sub-themes were identified in line with the research aims and objectives and questionnaire analysis:
- Classifying culpability;
- The importance of managing design;
- Prominent issues during the construction phase of works;
- Lack of quality design information impeding the contractor’s performance, and
- Requirements at tender stage.
4.3.2 Profile of Interview Participants
10 participants took part in the telephone interviews, to gain a broader understanding of their views on current design culpability in construction contracts, and provide further credibility on the data collected from the questionnaire.
Table 4.2: Demographic Profile of Interview Participants
4.3.3 Classifying Culpability
Interviewees generally acknowledged that vague contractual terms concerning the design culpability of the parties involved can be problematic, supporting Lai et al.’s (2004) views. Interviewee ‘D’ advised that the principle designers severely lack understanding of the contracts, “in the sense that they do not appreciate their responsibilities, which leads to confusion down the line” supporting Kraus and Scott’s (2009) discussions on the importance of understanding the contractual intentions.
Interviewee ‘A’ suggested that the principle designer should remain responsible for design coordination of the whole project and in doing so, “should be paid a realistic fee for this task”, however, this contradicts Interviewee ‘D’s’ opinion that they ‘lack understanding’.
Interviewee ‘D’ suggested that the problems lie with the design team and stated that, “the provision of the contractual terms are fine” which counters McKeeman and Rossetti’s (2007) judgements.
Interviewee ‘C’ concurs with interviewee ‘D’, expressing that the design team, “tend not to have the technical or practical skill and experience”, supporting Tzortzopoulos and Cooper’s (2015) depictions that they require a comprehensive skillset.
Interviewee ‘G’ highlights the problematic nature of classifying design culpability within D&B contracts suggesting that, “often contracts cannot have single point responsibility due to the complexity of the design or high-level finishes”.
Further to this, Pain and Bennett’s (1988) findings highlight that those working on projects with high level finishes, which involve contractor’s design, were generally less satisfied with the precision of the contractual terms. Thus, establishing that ‘high end’ design suffers from a lack of precise contractual provisions.
Interviewee ‘G’ stated that “too often the failings of a contract are not apparent until too far down the line”, linking to Castro’s (2009) statements and countering Miller (1982).
Interviewee ‘B’ considered that the design team must allocate CDPs, “according to a strict understanding of where design expertise resides”, assimilating Rowlinson’s (1987) suggestions along with McDonnell’s (2013) findings which highlight the necessity to “place the risk of loss on the party better able to bear it” (p.659).
Interviewee ‘E’ clarifies that in recent years’ design teams have given more risk to the contractors, he claimed that “eventually the clients will see this and more contracts will be design and build”.
It was acknowledged by Interviewee ‘I’ that only, “a contract which is wholly design and construct, or wholly construct only will have clearer design responsibilities than a contract which is construct only but with CDPs”.
4.3.4 The Importance of Managing Design
Interviewee ‘F’ believes that “the construction phase design manager should be involved in the project at tender stage (even if not full time) to further identify risk and opportunity”, supporting Hermalin’s (2008) suggestions. However, it was highlighted by Interviewee ‘A’ that the construction industry lacks sufficient supply of, “suitably qualified and experienced design managers to cope” with the management of design.
Interviewee ‘D’ concurs, suggesting that often even where design managers are available they, “lack the necessary training”.
Interviewee ‘G’ suggested that “with the rise in popularity of CDP elements, JCT should review their standard contract sets and further incorporate the CDP packages to include interfaces” which correlates with the 98% of respondents agreeing that interfaces require special care (Q10) alongside Circo’s (2006) findings.
They went on to say that the interfaces will require precise identification of design responsibility, “outlining an agreement going forward on how to manage interface CDP elements with the remaining design”, to ensure stakeholders understand their obligations.
4.3.5 Prominent Issues During the Construction Phase of Work
In correspondence to the questionnaire findings, Interviewee ‘I’ acknowledged that provision of employer’s information was a key issue, suggesting that, ”often the contract is let without the design being finalised”, McElroy et al. (2006) support this view. They went on to say that, “if it was, the client team would probably choose a different form of contract”.
In contrast to the questionnaire results, both interviewee’s ‘F’ and ‘G’ highlighted the approval of design packages an issue of main concern, with ‘F’ stating that “a robust approval process is essential but often unmanageable”. Interviewee ‘G’ recognised however that, “approval of CDPs in isolation to other trades can lead to problems”. Interviewee ‘C’ depicted the need to provide a framework that strictly precisely determines what is intended under the employer’s requirements, to ensure a systematic and ‘smooth’ process is achieved.
The requirement for this is further depicted in Circo’s (2006) conclusions. Not only did the interviewees suggest how design could be accurately defined to ensure stakeholders understand their obligations, Interviewee ‘G’ went on to say that, “CDPs further down the approval process can often come back to require late changes to the first sign off to accommodate unforeseen requirements”. This highlights the need to identify precise contract terms as the contract is formed to assist when issues such as this arise.
4.3.6 Lack of Quality Design Information Impeding the Contractor’s Performance
Respondents agreed that disputes could be avoided if quality design information was provided. Interviewee ‘H’s’ statement encased these views, “most problems or disputes within construction could be resolved or avoided by the provision of proper construction information, in an acceptable time for all other parties to fulfill their roles”.
This view was further asserted by interviewee ‘A’ who depicted that, “a lack of accurate, quality design information from the design team causes a multitude of issues with CDPs, and creates a situation of protracted design development often at the contractor’s expense”, which concurs with Lai et al.’s (2004) scholarly review. Further to this, McElroy et al.’s (2006) suggestions regarding the importance of timely completion of the design phase support these industry perspectives.
4.3.7 Requirements at Tender Stage
The discussions highlighted the insufficient time spent at tender stage to ensure detailed information is provided. This enables clear guidance for the contractor to carry out his duties and ensures that the parties involved have a common understanding of the intentions of those contractual terms written into the contract. Interviewee ‘J’ recommended that “any designer that wishes to propose the transfer of design responsibility should be forced to properly scope and specify the element concerned in the tender documents” supporting Kraus and Scott’s (2009) report to honor contractual intent.
Interviewee ‘B’ stated that there needs to be a focus on increasing the precision and detail in the contract, “highlighting where information is lacking”. They went on to say that it could be useful to implement a “template at tender stage for all packages, not just CDP items, particularly where information is lacking and could cause design issues, delays or disputes and thus have an impact on cost”, supporting Circo’s (2006) views.
Interviewee ‘A’ recommended that “design liability needs to be clearly identified from the tender stage, and not developed as the contract progresses”, which counters Lupton and Cornes (2013) view.
Interviewee ‘I’ went on to state that, “clearly defined rules of engagement, that are fair and reasonable for both parties” should be elicited. Both interviewees ‘C’ and ‘F’ concurred with this observation.
Interviewee ‘J’ emphasised that ultimately, “less adversarial contracts” need to be outlined to manage risk and accurately define design culpability, to ensure it doesn’t spiral out of control (McKeeman and Rossetti 2007).
4.4 Chapter Summary
This chapter highlighted the findings from the questionnaire and interviews, providing an analysis and comparison of the data collected.
5.0 Conclusions and Recommendations
5.1 Introduction
The findings from the literature review and primary data sources were collated and rigorous conclusions were formed with an initial summary from each section, followed by a review of the research objectives. Finally, recommendations to the construction industry along with suggestions for further research were presented.
5.2 Summary of Research Findings
5.2.1 Literature Review
- Vague language and a lack of precision in contractual provisions cause disputes between contracting parties, hence a clear definition of the responsibilities appointed to these parties is crucial.
- Where the lines of responsibility become blurred or overlap, it can lead to confusion between parties, and thus disagreements.
- Identification of where the risk lies is imperative, to ensure liability does not spiral out of control.
- It is crucial key project stakeholders interoperate and commonly understand the level of their design responsibility as the contract is formed.
- Accurately prepared employer’s requirements enable the contractor to progress with the project in a timely manner.
- Delays often attribute to construction works progressing prior to the completion of the design.
- A spectrum of liability is required to develop an understanding of what each level of design responsibility distinctly means, and expand the levels not only as two principles, but broadened into a scale that can be concisely drafted into contract clauses, as a robust solution.
- Where contractor’s designed portions are implemented, the following may benefit their clarity:
- The extent of the packages should be accurately defined, as points of connection and interfaces between CDP and non-CDP packages of work are cause for concern.
- It may be that at tender stage, the exact scope of items of work that are to be the contractor’s design is unknown. Where this occurs, procedures for the instruction of CDP items need to be distinctly noted in the contract terms and obeyed to ensure there is no doubt an item of work is or is not a CDP.
5.2.2 Questionnaires
- There are inherent problems regarding industries perception and understanding of the two distinct levels of liability.
- The likelihood of disputes due to the dual role of the design and build contractor elicited conflicting views, which may link to its increasing level of use in industry.
- An industry awareness of grey areas associated with CDPs and their common cause for disputes confirms the requirement to identify and clarify interfaces.
- Lack of CDP design acceptance correlated to a lengthier design process, having an overall effect on project completion dates.
- Contract provisions and employer’s requirements need to be stringent and clear to prevent manipulation and ensure that stakeholders are not led into a false sense of security.
- Poor specification followed by provision of information in a timely manner, were highlighted as the key issues for contractors throughout the construction phase of works.
- Refinements in contractual arrangements regarding design management are required, due to professionals seeking to limit their liability.
- Strong positive correlations were identified and illustrated in Table 5.1. Issues are expressed in ascending order of importance from left to right to demonstrate increasing correlations.
Table 5.1: Demonstration of Increasing correlations (Q5,6,10,11 & 13)
(-1= negative linear relationship, 0= no linear relationship, +1= perfect positive linear relationship)
5.2.3 Interviews
- It was acknowledged that the design team often lack the necessary understanding of contract provisions (inadequate training), along with practical skill, resulting in conflict as to the stakeholder’s interpretation of his liabilities.
- In recent years’ design teams have been shifting greater risk onto the contractor, which is likely to cause a change in the chosen procurement routes, towards single point responsibility.
- Design and build contracts lack the provisions and contractual ability to manage complex designs and high-level finishes. Therefore, further development is required if this procurement route is to be widely used, particularly in industry divisions such as high-end residential. Strategic items need to be considered when drafting contracts, between the D&B contractor and the designer to address these prevailing issues.
- Lack of suitably qualified and trained design managers to cope with the increasing demand for the management of design highlights a present issue within the UK construction industry.
- Establishment of interfaces within the contract terms, for CDP elements of design, were once again raised as imperative to avoid confusion and ultimately disputes. Specifically, how to manage these interfaces with the remaining design, to avoid assumptions due to overlaps.
- Quality design information would mitigate a high proportion of on-site disputes. This needs to be produced at tender stage, to provide clear guidance. Acknowledgement of where information is lacking which could cause design issues and delays would be advantageous.
- Resources in time and cost should be allowed for coordination of design drawings and a fee should be clearly identified in the tender price for that purpose.
5.3 Review of Research Objectives
5.3.1 Objective 1
To assess construction contracts
The initial exploratory research of this project aimed to gain a baseline understanding of the applicable construction contract obligations with regards to design responsibility. Objective 1 was covered within the scope of the literature review. The following tasks were set to meet Objective 1:
- A review of the development of construction contracts;
- Defining a construction contract and its binding nature in law;
- Understanding the express and implied obligations under The Joint Contracts Tribunal, as well as the New Engineering suite of contracts, and
- A review of both traditional and design and build procurement routes.
5.3.2 Objective 2
To review key roles of responsibility for design in contracts
A critical literature review of published information developed knowledge of the subject. Primary data highlighted industries perspectives on the contractual terms within construction contracts regarding design culpability. The objective was met through the following tasks:
- A review of the design culpability of professionals;
- Considering a ‘reasonable skill and care’ obligation, against a ‘fit for purpose’ obligation;
- A review of both the design teams and contractors design culpability under construction contracts, and
- Understanding design culpability in contract and tort.
5.3.3 Objective 3
To analyse case law which appraises the delineation of design responsibility in construction contracts
An appraisal of case law arising from disputes identified that ambiguous and blurred design responsibilities gave rise to contractual parties’ disagreements. The following tasks, enabled the objective to be met:
- Analysing relevant case law that appraises the delineation of design responsibility, and
- A review of what has been held, and the effect the decisions of these cases had upon future disputes, legislation and standard contract forms.
5.3.4 Objective 4
To explore companies and project stakeholder’s views concerning design culpability within projects and contracts
The appropriate tools and techniques were used, to gather the professional’s perspectives and place the results from the study into context. The objective was met through the following tasks:
- Compare literature and construction industries opinion of design culpability in construction contracts;
- Understand professionals view on what the risk for a stricter standard of design liability implicates;
- Gain industry professional’s opinions on the precision of current contractual provisions, the intentions of the parties involved and how design could be accurately defined to ensure stakeholders understand their obligations, and
- To understand the point of view of the contractor and whether they believe that D&B contracts provide a clear and defined set of obligations over and above traditional contracts with CDP portions, with regards to design responsibility and contract terms.
5.3.5 Objective 5
To produce guidance on understanding design responsibility
A presentation of specific conclusions related to the evidence, research problem and objectives highlighted industries current knowledge on the problem, and identified the areas that lacked clarity and thus necessitated further guidance. The objective was met through the following tasks:
- Provide a framework to determine the level of design culpability applicable to construction contracts, with the developed understanding of design liability following the literature review and conclusions found from the data collection, and
- Split the two foremost levels of design liability into a spectrum, to produce a clear, concise, unambiguous frame which can be followed by industry professionals entering a construction contract, to fully understand their duties
5.4 Recommendations to Industry
The recommendations, derived from the findings of the survey and interviews, encapsulate the contract strategies and key parameters to be adopted to prepare and draft a well-coordinated set of contracts to aid assignment of design culpability concerning project participants. The findings highlighted a lack of suitably qualified and trained design managers to cope with the rising pressure of their role. design and build contractors must acquire the appropriate design managers to communicate effectively with their design consultants.
Suitable investments should be made to train competent managers. Not only do design managers require extra professional skills to cope with the increasing complexities and demands of modern practice, but also the design team. It was acknowledged that the design team often lack the necessary understanding of contract provisions, along with practical skill, resulting in conflict as to the stakeholder’s liabilities. This could be linked contractual parties interpreting the contract terms differently. However, it is crucial that project participants understand their legal exposure regarding design culpability.
Interfaces between CDP and non-CDP items should be highlighted in the contract documents with a clear allocation of where the line of responsibility starts and stops for each stakeholder to avoid confusion and the opportunity for disputes. It could be said that design and build contracts overcome this grey area of responsibility as the contractor is liable for both design and construction, however, design and build contracts lack the necessary provisions and contractual ability to manage complex designs and/ or high level finishes. Hence, further development is required if this procurement route is to be widely used, particularly in industry divisions such as high end residential.
A shift towards a higher level of input at tender stage could provide clear guidance, in addition to acknowledgement of where information is lacking. Vague language and a lack of precision in contractual provisions causes disputes between contracting parties, thus a clear definition of the responsibilities appointed to these parties is crucial, which supports the research hypothesis: The clear delineation of design responsibility will require the contractual parties to precisely define the contractual contingencies at the time the contract is formed, as well as ensure the stakeholders have the same intentions and understanding of these provisions.
Going forward, a template at tender stage for all packages, including contractor’s design, could highlight interfaces of design in addition to where information is lacking, to reduce the likelihood of design issues, delays and disputes, all of which impact the project’s overall cost. Within this framework, implementing a spectrum of liability which identifies levels of responsibility and their distinct meanings and implications, would assist in founding a robust solution. Identification of where the risk lies (for design) is imperative, to ensure liability does not spiral out of control, through precise and stringent contractual provisions.
It is foreseeable that improved contract forms will emerge to better assist stakeholders’ interests concerning design culpability. If D&B procurement routes continue to rise in popularity, the inability to insure a fitness for purpose obligation needs to be well-defined and if possible remedied, to prevent confusion and parties becoming reluctant to undertake the dual-role of responsibility.
5.5 Limitations of the Study
The research has predominantly focused on JCT and NEC contract forms, considering only their contract provisions and allocation of design culpability. The client’s perspective, along with the design team and subcontractor’s views were predominantly missed from the study. The data collection and analysis incorporated only the contractor’s viewpoints, the inclusion of the other project stakeholders would have strengthened the credibility of the research by collating their opinions.
5.6 Recommendations for Further Research
Based on the limitations of the study, the below remarks represent recommendations for further research:
- Gather representative views of the delineation of design culpability from employers, design teams, and subcontractors to strengthen the validation of the research problem and identification of findings;
- Seek understanding of the constraints design and build construction contracts have on the ability to procure projects with high end design and finishes;
- Uncover how contractors with only experience in construction will cope with the emerging D&B market, and
- Review the inability to secure professional indemnity insurance on a ‘fit for purpose’ obligation, and how contractors can protect themselves under a D&B contract.
References
Amaratunga, D., Baldry, D., Sarshar, M. and Newton, R. (2002). Quantitative and qualitative research in the built environment: application of “mixed” research approach. Work Study, [online] 51(1). Available at: http://eprints.uwe.ac.uk/9190/ [Accessed 20 Mar. 2017].
Adriaanse, J. (2016). Construction contract law. 4th ed. London: Palgrave Macmillan.
Ahmed, V., Opoku, A. and Aziz, Z. (2016). Research Methodology in the Built Environment: A Selection of Case Studies. 1st ed. Routledge.
Castro, J. (2009). Evolving Liability for Design-Build Contracts: The Perfect Storm of Conflicting Interests. pp.1-31.
Chan E.H and Chan A.P.C. (2000). Design-Build Contracts in Hong Kong – Some Legal Concerns, Information and Communication in Construction Procurement, Serpell, A (ed.). Pontificia Universidad Catolica de Chile, Chile, 183-200.
Chan, E. and Yu, A. (2005). Contract strategy for design management in the design and build system. International Journal of Project Management, 23(8), pp.630-639.
Chan, E., Chan, A. and Yu, A. (2005). Design Management in Design and Build Projects: The New Role of the Contractor. pp.1-11.
Circo, C. (2005). When Specialty Designs Cause Building Disasters: Responsibility for Shared Architectural and Engineering Services. Nebraska Law Review, [online] 84(1). Available at: http://h p://digitalcommons.unl.edu/nlr/vol84/iss1/4 [Accessed 16 Oct. 2016].
Circo, C. (2006). Contract Theory and Contract Practice: Allocating Design Responsibility in the Construction Industry. pp.561-638.
Creswell, J. (2013). Research Design: Qualitative, Quantitative and Mixed Methods Approaches. 4th ed. Los Angeles, Calif.: Sage.
Doloi, H. (2008). Analysing the novated design and construct contract from the client's, design team's and contractor's perspectives. Construction Management and Economics, 26(11), pp.1181-1196.
Fellows, R. and Liu, A. (2015). Research Methods for Construction. 4th ed. John Wiley & Sons.
Fraenkel, J. and Wallen, N. (1993). How to Design and Evaluate Research in Education.
Gaafar, H. and Perry, J. (1999). Limitation of design liability for contractors. International Journal of Project Management, [online] 17(5), pp.301-308. Available at: http://www.sciencedirect.com/science/article/pii/S0263786398000465 [Accessed 16 Oct. 2016].
Hermalin, B. (2008). Vague Terms: Contracting when Precision in Terms is Infeasible. Journal of Institutional and Theoretical Economics JITE, 164(1), pp.76-94.
Holub, C. (2017). Theories of Liability Against Design Professionals. Porter and Hedges, pp.1-28.
Hughes, W., Murdoch, J. and Champion, R. (2015). Construction Contracts Law and Management. 5th ed. New York: Routledge.
Ibm.com. (2017). International Business Machines (IBM) SPSS - IBM Analytics. [online] Available at: https://www.ibm.com/analytics/us/en/technology/spss/ [Accessed 20 Mar. 2017].
Institution of Civil Engineers. (2013). NEC3 Engineering and Construction Contract. 1st ed. Glasgow: Bell & Bain Limited.
Jackson, R. and Powell, J. (1992). Professional Negligence. 3rd ed. Sweet & Maxwell.
Johnson, R. and Onwuegbuzie, A. (2004). Mixed Methods Research: A Research Paradigm Whose Time Has Come. Educational Researcher, [online] 33(7), pp.14-26. Available at: http://edr.sagepub.com/content/33/7/14.short [Accessed 20 Mar. 2017].
Johnson, R. and Turner, L. (2002). Sage handbook of mixed methods in social & behavioral research. 1st ed. Los Angeles: Sage.
Kerlinger, F. (1979). Behavioral Research. 1st ed. New York: Holt, Rinehart and Winston.
Kothari, C. (2004). Research Methodology: Methods and Techniques. 1st ed. New Age International Pvt Ltd Publishers.
Kraus, J. and Scott, R. (2009). Contract Design and the Structure of Contractual Intent. [online] pp.1-68. Available at: https://www.law.virginia.edu/pdf/workshops/0708/kraus.pdf [Accessed 6 Oct. 2016].
Lai, J., Yik, F. and Jones, P. (2004). Disputes arising from vaguely defined contractual responsibilities in building services maintenance contracts. Facilities, 22(1/2), pp.44-52.
Latham, S. (1994). Constructing the Team. [online] Stationery Office Books, pp.1-140. Available at: https://pdfs.semanticscholar.org/bed6/02d037ee26af24746b3021bbaf7184374d12.pdf [Accessed 4 Nov. 2016].
Lupton, S. (2015). Design Liability: Problems With Defining Extent and Level. [online] Available at: https://i-law.com/ilaw/doc/view.htm?id=363089 [Accessed 2 Nov. 2016].
Lupton, S. and Cornes, D. (2013). Cornes and Lupton’s Design Liability in the Construction Industry. 5th ed. London: Wiley-Blackwell.
Marshall, T. (2011). Design liability in English law. 6(2), pp.15-20.
Martimianakis, M., Maniate, J. and Hodges, B. (2009). Sociological interpretations of professionalism. Medical Education, 43(9), pp.829-837.
Mathers, N., Fox, N. and Hunn, A. (2010). Surveys and Questionnaires. pp.2-3.
McDonnell, B. (2013). Finding a Contract in the “Muddle”: Tracing the Source of Design Professionals’ Liability in the Construction Context Under Washington’s Independent Duty Doctrine. Gonzaga Law Review, 48(3), pp.627- 672.
McElroy, M., Friedlander, M. and Rowe, H. (2006). Responsibilities and Liabilities of Architects and Engineers for Construction Failures. Construction Litigation.
McKeeman, M. and Rossetti, K. (2007). Contractors’ Tort Claims Leave Design Professionals Wondering if Liability is Spiralling Out of Control. Cost Engineering, [online] 49(10). Available at: http://ezproxy.massey.ac.nz/login?url=http://search.ebscohost.com/login.aspx?direct=true&db=bth&AN=27329451&site=eds-live&scope=site. [Accessed 18 Oct. 2016].
Miller, B. (1982). The Architect in the Design-Build Model: Designing and Building the Case for Strict Liability in Tort. Case Western Reserve Law Review, [online] 33(1). Available at: http://h p://scholarlycommons.law.case.edu/caselrev/vol33/iss1/8 [Accessed 12 Nov. 2016].
Naoum, S. (2013). Dissertation Research & Writing for Construction Students. 3rd ed. Abingdon, Oxon: Routledge.
Network Rail Schedule of Amendments to JCT DB 2016 Design and Build Contract. (2016). 1st ed. Network Rail Infrastructure Limited.
Office of Government and Commerce, (2007). Achieving Excellence in Construction. [online] Available at: https://www.dfpni.gov.uk/articles/achieving-excellence-construction-initiative [Accessed 21 Oct. 2016].
Onwuegbuzie, A. and Leech, N. (2005). On Becoming a Pragmatic Researcher: The Importance of Combining Quantitative and Qualitative Research Methodologies. International Journal of Social Research Methodology, 8(5), pp.375-387.
Pain, J. and Bennett, J. (1988). JCT With Contractor's Design form of contract: a study in use. Construction Management and Economics, 6(4), pp.307-337.
Punch, K. (2013). Introduction to Social Research: Quantitative and Qualitative Approaches. 1st ed. Los Angeles, Calif: SAGE.
Ramachandra, T. (2013). Exploring Feasible Solutions to Payment Problems in the Construction Industry in New Zealand. Doctor of Philosophy (PhD). Auckland University of Technology.
Rowlinson, S. (1987). Design Build - Its Development and Present Status. Occasional paper, No. 36, The Chartered Institute of Building, Ascot.
Surveymonkey.co.uk. (2017). SurveyMonkey: Free online survey software & questionnaire tool. [online] Available at: https://www.surveymonkey.co.uk [Accessed 8 Feb. 2017].
Tam, C.M. (2000). Design and Build on complicated redevelopment project in Hong Kong: The Happy Valley Racecourse Redevelopment, International Journal of Project Management, 18(2), 125-129.
Tashakkori, A. and Teddlie, C. (2002). Handbook of Mixed Methods in Social & Behavioral Research. 1st ed. Los Angeles: Sage.
The Joint Contracts Tribunal. (2013). Implied Fitness for Purpose Obligations. JCT News, p.8.
The Joint Contracts Tribunal. (2016). Design and Build Contract (DB). 1st ed. London: Sweet & Maxwell.
The Joint Contracts Tribunal. (2016). Standard Building Contract with Quantities (SBC/Q). 1st ed. London: Sweet & Maxwell. Turina, N., Radujkovic, M. and Car-Pusic, D. (2008). Design and Build in Comparison with the Traditional Procurement Method and the Possibility of its Application in the Croatian Construction Industry.
Tzortzopoulos, P. and Cooper, R. (2015). Design management from a contractor’s perspective: the need for clarity. Doctor of Philosophy (PhD). University of Huddersfield.
Victor O. Schinnerer and Company Inc. (2017). Legal Liability of Design Professionals. pp.1-28.
Waterhouse, R., Peckett, V., Malleson, A. and Beaumont, B. (2015). National Construction Contracts and Law Survey.
Wiesner, W. and Cronshaw, S. (1988). A meta-analytic investigation of the impact of interview format and degree of structure on the validity of the employment interview*. Journal of Occupational Psychology, 61(4), pp.275-290.
Appendices
REQUIRED APPENDICES
Appendix A: Project Definition Document & Gantt Chart
Appendix B: Health and Safety Risk Assessment
Appendix C: Ethical Clearance Email
Appendix D: Participant Information Sheet
Appendix E: Blank Informed Consent
DISSERTATION APPENDICES
Appendix F: Questionnaire Survey Questions
Appendix G: SPSS (Statistical Package for the Social Sciences) Data Tables
Appendix H: Telephone Interview Transcripts
Appendix A: Project Definition Document
Appendix A: Gantt Chart
Appendix B: Health and Safety Risk Assessment
Appendix C: Ethical Clearance Email
Appendix D: Participant Information Sheet
Appendix E: Black Informed Consent
Appendix F: Questionnaire Survey Questions
- Please specify your job role
- Design Manager
- Quantity Surveyor
- Commercial Manager
- Project Manager
- Site Manager
- Director
- Legal Professionals
- Other (please specify)
- How long have you worked in the construction industry?
- <5 years
- 6-10 years
- 11-15 years
- >15 years
Strongly Agree/ Agree/ Neutral / Disagree / Strongly Disagree
- Clear Contractual provisions reduce the likelihood of disputes
- The dual role of a design and build contractor has presented quite a challenge in determining the level of his responsibility
- Contractor's Design Portions have grey areas as to the extent of their liability
- Contractor's Design Portions are a common cause for disputes between parties
- Single Point responsibility is less conflicting than split culpability, as the contractor is responsible for both design and construction of the works
- The client team are best placed to prepare and approve the design, they should remain responsible for design coordination of the whole project
- The employer/design team often insist on specific subcontractors for CDP elements of work, even though they are one of a few listed, to avoid liability
- Interfaces between CDP/non-CDP items require special care
- It is very important and yet difficult to agree upon how the Contractor's Proposal for design has met the Employer's Requirement.
- As the contractor, which do you deem to be the most difficult issues during the construction phase?
- Provision of Employers Information
- Poor Specification
- Employers Variations and Instructions
- Unclear line of responsibility regarding design elements
- Approval of design packages
- Which standard of care is strict?
- An obligation to use reasonable skill and care
- A guarantee that the design will be fit for its intended purpose
- In what priority of importance are design management and design responsibility compared with the other factors such as single point responsibility, cost certainty, constructability and shorter project duration?
- Design Management and responsibility are less important than these other factors
- Design Management and responsibility are more important than these other factors
- All have equal importance
- Other (please specify)
- To what extent of design liability should a D&B contractor be responsible?
- An obligation to use reasonable skill and care
- A guarantee that the design will be fit for its intended purpose
- If you would like to participate in an interview, please could you leave your contact details in the box below
Appendix G: SPSS (Statistical Package for the Social Sciences) Data Table
Pearson Coefficient of Correlation Q5: Contractor's Design Portions have grey areas as to the extent of their liability
Correlations | |||
Profession | Opinion | ||
Profession | Pearson Correlation | 1 | .704** |
Sig. (2-tailed) | .000 | ||
N | 46 | 46 | |
Opinion | Pearson Correlation | .704** | 1 |
Sig. (2-tailed) | .000 | ||
N | 46 | 46 | |
**. Correlation is significant at the 0.01 level (2-tailed). |
Q6: Contractor’s Design Portions are a common cause for disputes between parties
Opinion
Correlations | |||
Experience | |||
Experience | Pearson Correlation | 1 | .836** |
Sig. (2-tailed) | .000 | ||
N | 46 | 46 | |
Opinion | Pearson Correlation | .836** | 1 |
Sig. (2-tailed) | .000 | ||
N | 46 | 49 | |
**. Correlation is significant at the 0.01 level (2-tailed). | |||
Q10: Interfaces between CDP/non-CDP items require special care
Correlations | |||
Profession | Opinion | ||
Profession | Pearson Correlation | 1 | .494** |
Sig. (2-tailed) | .000 | ||
N | 46 | 46 | |
Opinion | Pearson Correlation | .494** | 1 |
Sig. (2-tailed) | .000 | ||
N | 46 | 46 | |
**. Correlation is significant at the 0.01 level (2-tailed). |
Q11: It is very important and yet difficult to agree upon how the Contractor's Proposal for design has met the Employer's Requirement.
Correlations | |||
Experience | Opinion | ||
Experience | Pearson Correlation | 1 | .438** |
Sig. (2-tailed) | .002 | ||
N | 46 | 46 | |
Opinion | Pearson Correlation | .438** | 1 |
Sig. (2-tailed) | .002 | ||
N | 46 | 46 | |
**. Correlation is significant at the 0.01 level (2-tailed). |
Q13: Which standard of care is strict?
Correlations | |||
Experience | Level | ||
Experience | Pearson Correlation | 1 | .814** |
Sig. (2-tailed) | .000 | ||
N | 46 | 46 | |
Level | Pearson Correlation | .814** | 1 |
Sig. (2-tailed) | .000 | ||
N | 46 | 46 | |
**. Correlation is significant at the 0.01 level (2-tailed). |
Cross tabulation Q3: Clear Contractual Provisions Reduce the Likelihood of Disputes
Experience * Opinion Cross tabulation | ||||||
Opinion | Total | |||||
Strongly Agree | Agree | Neutral | Disagree | |||
Experience | >15 | 12 | 9 | 1 | 1 | 23 |
11-15 | 1 | 2 | 0 | 0 | 3 | |
6-10 | 3 | 2 | 0 | 0 | 5 | |
<5 | 3 | 9 | 2 | 1 | 15 | |
Total | 19 | 22 | 3 | 2 | 46 |
Q4: The dual role of a design and build contractor has presented quite a challenge in determining the level of his responsibility
Experience * Opinion Cross tabulation | |||||||
Opinion | Total | ||||||
Strongly Agree | Agree | Neutral | Disagree | Strongly Disagree | |||
Experience | >15 | 3 | 5 | 3 | 11 | 1 | 23 |
11-15 | 0 | 1 | 0 | 2 | 0 | 3 | |
6-10 | 0 | 2 | 2 | 1 | 0 | 5 | |
<5 | 0 | 10 | 3 | 2 | 0 | 15 | |
Total | 3 | 18 | 8 | 16 | 1 | 46 |
Q5: CDPs have Grey Areas as to the Extent of their Culpability
Profession * Opinion Cross tabulation | ||||||
Opinion | Total | |||||
Strongly Agree | Agree | Neutral | Disagree | |||
Profession | Design Manager | 12 | 2 | 0 | 0 | 14 |
Project Manager | 0 | 6 | 3 | 0 | 9 | |
Commercial Manager | 0 | 5 | 2 | 0 | 7 | |
Quantity Surveyor | 0 | 4 | 2 | 0 | 6 | |
Legal Professional | 0 | 1 | 3 | 0 | 4 | |
Director | 0 | 3 | 0 | 0 | 3 | |
Site Manager | 0 | 0 | 1 | 1 | 2 | |
Other | 0 | 0 | 0 | 1 | 1 | |
Total | 12 | 21 | 11 | 2 | 46 |
Q6: CDPs are a Common Cause for Disputes Between Parties
Experience * Opinion Cross tabulation | ||||||
Opinion | Total | |||||
Strongly Agree | Agree | Neutral | Disagree | |||
Experience | >15 | 7 | 12 | 3 | 1 | 23 |
11-15 | 1 | 2 | 0 | 0 | 3 | |
6-10 | 4 | 1 | 0 | 0 | 5 | |
<5 | 6 | 8 | 1 | 0 | 15 | |
Total | 18 | 23 | 4 | 1 | 46 |
Q7: Single Point responsibility is less conflicting than split culpability, as the contractor is responsible for both design and construction of the works
Experience * Opinion Cross tabulation | |||||||
Opinion | Total | ||||||
Strongly Agree | Agree | Neutral | Disagree | Strongly Disagree | |||
Experience | >15 | 6 | 11 | 3 | 1 | 2 | 23 |
11-15 | 0 | 1 | 1 | 0 | 1 | 3 | |
6-10 | 1 | 4 | 0 | 0 | 0 | 5 | |
<5 | 1 | 9 | 3 | 2 | 0 | 15 | |
Total | 8 | 25 | 7 | 3 | 3 | 46 |
Q8: The client team are best placed to prepare and approve the design; they should remain responsible for design coordination of the whole project
Experience * Opinion Cross tabulation | ||||||
Opinion | Total | |||||
Strongly Agree | Agree | Neutral | Disagree | |||
Experience | >15 | 4 | 9 | 8 | 2 | 23 |
11-15 | 0 | 3 | 0 | 0 | 3 | |
6-10 | 0 | 2 | 2 | 1 | 5 | |
<5 | 0 | 6 | 5 | 4 | 15 | |
Total | 4 | 20 | 15 | 7 | 46 |
Q9: The employer/design team often insist on specific subcontractors for CDP elements of work, even though they are one of a few listed, to avoid liability
Experience * Opinion Cross tabulation | ||||||
Opinion | Total | |||||
Strongly Agree | Agree | Neutral | Disagree | |||
Experience | >15 | 5 | 14 | 4 | 0 | 23 |
11-15 | 0 | 2 | 1 | 0 | 3 | |
6-10 | 1 | 2 | 1 | 1 | 5 | |
<5 | 1 | 10 | 2 | 2 | 15 | |
Total | 7 | 28 | 8 | 3 | 46 |
Q10: Interfaces Between CDP and Non-CDP Items Require Special Care
Profession * Opinion Cross tabulation | ||||||
Opinion | Total | |||||
Strongly Agree | Agree | Neutral | Disagree | |||
Profession | Design Manager | 10 | 4 | 0 | 0 | 14 |
Project Manager | 0 | 4 | 5 | 0 | 9 | |
Commercial Manager | 2 | 4 | 1 | 0 | 7 | |
Quantity Surveyor | 1 | 4 | 1 | 0 | 6 | |
Legal Professional | 0 | 3 | 1 | 0 | 4 | |
Director | 1 | 2 | 0 | 0 | 3 | |
Site Manager | 0 | 0 | 1 | 1 | 2 | |
Other | 0 | 0 | 0 | 1 | 1 | |
Total | 14 | 21 | 9 | 2 | 46 |
Q11: It is very important and yet difficult to agree upon how the Contractor's Proposal for design has met the Employer's Requirement.
Experience * Opinion Cross tabulation | ||||||
Opinion | Total | |||||
Strongly Agree | Agree | Neutral | Disagree | |||
Experience | >15 | 10 | 11 | 1 | 1 | 23 |
11-15 | 1 | 2 | 0 | 0 | 3 | |
6-10 | 2 | 1 | 1 | 1 | 5 | |
<5 | 2 | 4 | 7 | 2 | 15 | |
Total | 15 | 18 | 9 | 4 | 46 |
Q13: Which Standard of Care is strict?
Experience * Level Cross tabulation | ||||
Level | Total | |||
A guarantee that the design will be fit for its intended purpose | An obligation to use reasonable skill and care | |||
Experience | >15 | 22 | 1 | 23 |
11-15 | 2 | 1 | 3 | |
6-10 | 2 | 3 | 5 | |
<5 | 1 | 14 | 15 | |
Total | 27 | 19 | 46 |
Q14: In what priority of importance are design management and design responsibility compared with the other factors such as single point responsibility, cost certainty, constructability and shorter project duration?
Experience * Importance Cross tabulation | ||||||
Importance | Total | |||||
Less Important | More Important | Equal Importance | Other | |||
Experience | >15 | 1 | 4 | 16 | 2 | 23 |
11-15 | 1 | 0 | 2 | 0 | 3 | |
6-10 | 0 | 0 | 5 | 0 | 5 | |
<5 | 1 | 2 | 12 | 0 | 15 | |
Total | 3 | 6 | 35 | 2 | 46 |
Two-tailed Independent T-Test Q3: Clear Contractual Provisions Reduce the Likelihood of Disputes
One-Sample Statistics | ||||
N | Mean | Std. Deviation | Std. Error Mean | |
Importance | 46 | 2.7826 | .62939 | .09280 |
Q4: The dual role of a design and build contractor has presented quite a challenge in determining the level of his responsibility
One-Sample Statistics | ||||
N | Mean | Std. Deviation | Std. Error Mean | |
Opinion | 46 | 2.8696 | 1.04581 | .15420 |
Q5: CDPs have Grey Areas as to the Extent of their Culpability & Q10: Interfaces Between CDP and Non-CDP Items Require Special Care
One-Sample Test | ||||||
Test Value = 0 | ||||||
t | df | Sig. (2-tailed) | Mean Difference | 95% Confidence Interval of the Difference | ||
Lower | Upper | |||||
Special Care | 11.776 | 13 | .000 | 1.14286 | .9332 | 1.3525 |
Grey Areas | 10.262 | 13 | .000 | 1.28571 | 1.0150 | 1.5564 |
Q6: CDPs are a Common Cause for Disputes Between Parties
One-Sample Statistics | ||||
N | Mean | Std. Deviation | Std. Error Mean | |
Opinion | 46 | 2.3043 | 1.05134 | .15501 |
Q7: Single Point responsibility is less conflicting than split culpability, as the contractor is responsible for both design and construction of the works
One-Sample Statistics | ||||
N | Mean | Std. Deviation | Std. Error Mean | |
Opinion | 46 | 1.7391 | .77272 | .11393 |
Q8: The client team are best placed to prepare and approve the design; they should remain responsible for design coordination of the whole project
One-Sample Statistics | ||||
N | Mean | Std. Deviation | Std. Error Mean | |
Level | 46 | 1.2391 | .43127 | .06359 |
Q9: The employer/design team often insist on specific subcontractors for CDP elements of work, even though they are one of a few listed, to avoid liability
One-Sample Statistics | ||||
N | Mean | Std. Deviation | Std. Error Mean | |
Opinion | 46 | 2.1522 | .75916 | .11193 |
Q11: It is very important and yet difficult to agree upon how the Contractor's Proposal for design has met the Employer's Requirement.
One-Sample Test | ||||||
Test Value = 0 | ||||||
t | df | Sig. (2-tailed) | Mean Difference | 95% Confidence Interval of the Difference | ||
Lower | Upper | |||||
Experience | 11.166 | 45 | .000 | 2.26087 | 1.8530 | 2.6687 |
Opinion | 14.716 | 45 | .000 | 2.04348 | 1.7638 | 2.3232 |
Q12: As the contractor, which do you deem to be the most difficult issues during the construction phase?
One-Sample Statistics | ||||
N | Mean | Std. Deviation | Std. Error Mean | |
Opinion | 46 | 1.7391 | .71289 | .10511 |
Q14: In what priority of importance are design management and design responsibility compared with the other factors such as single point responsibility, cost certainty, constructability and shorter project duration?
One-Sample Statistics | ||||
N | Mean | Std. Deviation | Std. Error Mean | |
Opinion | 46 | 2.1739 | .85126 | .12551 |
Appendix H: Telephone Interview Transcripts
Interviewee: A
Profession: Commercial Manager
Experience: 23 Years
Duration: 0:03:15
Date: 13th March
Interviewer: As I’m sure you will know, I am just calling to gain a deeper understanding of your perspectives and options on the survey you participated in. If it is alright with you, I am going to pose a single question and if you wouldn’t mind discussing your thoughts on the matter.
Interviewee: Yes of course.
Interviewer: Further to the opinions you expressed in the questionnaire, please could you comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved. Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations.
Interviewee: Ok yes — I’ll start with design responsibility as I believe that the principal designer should remain responsible for design coordination of the entire project and should be paid a realistic fee for this task.
Interviewer: Is there a reason you feel they are best placed to manage and coordinate the design? And if so, do you feel there is a better way to define contract clauses that specifically set this out?
Interviewee: I believe that design liability needs to be clearly identified from tender stage, and not developed as the contract progresses to hopefully avoid disagreements, however it is the contract clauses that need to be precisely identified to help with that I think.
Interviewer: So, do you feel the contract clauses are inaccurate?
Interviewee: Yes, I believe so, but further to that I feel it can often be the design team’s information that causes inaccuracy —a lack of accurate, quality design information from the design team causes a multitude of issues with contractor’s designed portions and creates a situation of protracted design development often at the contractor’s expense — going back to my previous point, I feel the design team is best placed to manage design as currently the industry lacks and we do not provide suitably qualified and experienced design managers to cope.
Interviewer: Ok thank you for your opinions, good bye.
Interviewee: B
Profession: Design Manager
Experience: 16 Years
Duration: 0:02:29
Date: 13th March
Interviewer: As I’m sure you will know, I am just calling to gain a deeper understanding of your perspectives and options on the survey you participated in. If it is alright with you, I am going to pose a single question and if you wouldn’t mind discussing your thoughts on the matter.
Interviewee: No problem.
Interviewer: Further to the opinions you expressed in the questionnaire, please could you comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved. Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations.
Interviewee: Yeah sure, as a design manager I concentrate mostly on CDP packages and therefore my key concerns surround them. I feel the client’s design team must ensure that CDP's are allocated according to a strict understanding of where design expertise resides. If it isn't in the contractors supply chain, then it shouldn't be a CDP.
Interviewer: Ok, do you have any other comments?
Interviewee: There should be a focus on agreeing the Contractors Proposals and Employers Requirements using as much detail where possible and highlighting where information is lacking.
Interviewer: How do you propose this could be enforced going forward?
Interviewee: Going forward it could be worth using this template at tender stage for all packages not just CDP items. Particularly where information is lacking and could cause design issues, delays or disputes— and thus have an impact on cost.
Interviewer: Thank you for your time, good bye.
Interviewee: C
Profession: Quantity Surveyor
Experience: 12 Years
Duration: 0:01:42
Date: 13th March
Interviewer: As I’m sure you will know, I am just calling to gain a deeper understanding of your perspectives and options on the survey you participated in. If it is alright with you, I am going to pose a single question and if you wouldn’t mind discussing your thoughts on the matter.
Interviewee: Of course.
Interviewer: Further to the opinions you expressed in the questionnaire, please could you comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved. Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations.
Interviewee: Right, ok — well honestly, I feel as though aarchitects and designers tend not to have the technical or practical skill and experience — after all the definition of architect is master builder.
Interviewer: Any further remarks?
Interviewee: Along with that I believe that the design team issues unclear employer’s requirements and to ensure a smooth-running project clear speciation’s need to be highlighted from the outset. Interviewer: Ok, thank you very much for your time. Good bye.
Interviewee: D
Profession: Design Manager
Experience: 6 Years
Duration: 0:02:02
Date: 14th March
Interviewer: As I’m sure you will know, I am just calling to gain a deeper understanding of your perspectives and options on the survey you participated in. If it is alright with you, I am going to pose a single question and if you wouldn’t mind discussing your thoughts on the matter.
Interviewee: Yes go for it.
Interviewer: Further to the opinions you expressed in the questionnaire, please could you comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved. Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations.
Interviewee: Yeah, the provision of the contractual terms are fine — it’s that the understanding of these contracts and their definitions is severely lacking from the consultant teams generally in the sense that they do not appreciate their responsibilities that leads to confusion down the line.
Interviewer: Any further comments?
Interviewee: I just feel as those consultants need a greater understanding, maybe they lack the necessary training with regards to contracts and their terms —alongside a lack of understanding what their responsibilities and what they have signed up to.
Interviewer: Ok, thank you for your opinions and time, good bye.
Interviewee: E
Profession: Project Manager
Experience: 18 Years
Duration: 0:0:42
Date: 14th March
Interviewer: As I’m sure you will know, I am just calling to gain a deeper understanding of your perspectives and options on the survey you participated in. If it is alright with you, I am going to pose a single question and if you wouldn’t mind discussing your thoughts on the matter.
Interviewee: Yeah, no problem.
Interviewer: Further to the opinions you expressed in the questionnaire, please could you comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved. Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations.
Interviewee: My comment is regarding risk allocation, I have noticed that design teams in recent years have given more and more risk to the contractors. Which I see resulting in more and more contractors opting for design and build procurement routes — eventually the clients will see this and more contracts will be design and build.
Interviewer: Thank you for your perspective, good bye.
Interviewee: F
Profession: Design Manager
Experience: 8 Years
Duration: 0:01:39
Date: 15th March
Interviewer: As I’m sure you will know, I am just calling to gain a deeper understanding of your perspectives and options on the survey you participated in. If it is alright with you, I am going to pose a single question and if you wouldn’t mind discussing your thoughts on the matter.
Interviewee: Yes of course.
Interviewer: Further to the opinions you expressed in the questionnaire, please could you comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved. Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations.
Interviewee: Ok right, regarding design acceptance, a robust approval process is essential but often unmanageable, for example — if a two-week approval period is allowed then the re-draw period is never enough.
Interviewer: Do you have any further comments?
Interviewee: Clear and concise documentation within the contract which identifies who is responsible for what would be extremely beneficial so that when complications and disputes arise, the contract sets out the requirements and those responsible firmly.
Interviewer: Ok thank you.
Interviewee: Oh and to add — I believe the construction phase Design Manager should be involved in the project at tender stage, even if not full time, to further identify risk and opportunity.
Interviewer: Thank you for your time, good bye.
Interviewee: G
Profession: Design Manager
Experience: 17 Years
Duration: 0:03:09
Date: 15th March
Interviewer: As I’m sure you will know, I am just calling to gain a deeper understanding of your perspectives and options on the survey you participated in. If it is alright with you, I am going to pose a single question and if you wouldn’t mind discussing your thoughts on the matter.
Interviewee: Ok.
Interviewer: Further to the opinions you expressed in the questionnaire, please could you comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved. Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations.
Interviewee: Yes, I have a few comments — regarding contractor’s design — approval of CDPs in isolation to other trades can lead to problems — CDP's further down the approval process can often come back to require late changes to the first sign off in order to accommodate unforeseen requirements.
Interviewer: Anything other comments?
Interviewee: With the rise in popularity of CDP elements, I believe that JCT should review their standard contracts set and further incorporate the CDP packages to include interfaces — specifically to identify design responsibility for interfaces or outline an agreement going forward on how to manage interface CDP elements with the remaining design.
Interviewer: Thank you for your comments.
Interviewee: As a contractor working on high end residential projects mostly, I have a comment regarding design and build contract procurement — although I feel it is a beneficial route of construction, as we would be wholly responsible and in charge of our decisions, some contracts cannot have D&B single point responsibility due to complexity of the design / high level finishes — it should be highlighted that all too often the failings of a contract are not apparent until too far down the line.
Interviewer: Ok thank you for your perspective, good bye.
Interviewee: H
Profession: Director
Experience: 32 Years
Duration: 0:01:12
Date: 16th March
Interviewer: As I’m sure you will know, I am just calling to gain a deeper understanding of your perspectives and options on the survey you participated in. If it is alright with you, I am going to pose a single question and if you wouldn’t mind discussing your thoughts on the matter.
Interviewee: Yeah, no problem.
Interviewer: Further to the opinions you expressed in the questionnaire, please could you comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved. Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations.
Interviewee: Yes, I feel as though, as the contractor, we need to continue to request more detailed tender/construction information to ensure we can progress in the construction phase of work steadily without having to go back to the design team and wait for further instruction, agreements or alterations.
Interviewer: Any further comments on that?
Interviewee: Most problems — disputes within construction could be resolved or avoided by the provision of proper construction information in adequate time for all other parties to fulfill their roles.
Interviewer: Ok thank you for your opinions, good bye.
Interviewee: I
Profession: Legal Professional
Experience: 9 Years
Duration: 0:01:06
Date: 17th March
Interviewer: As I’m sure you will know, I am just calling to gain a deeper understanding of your perspectives and options on the survey you participated in. If it is alright with you, I am going to pose a single question and if you wouldn’t mind discussing your thoughts on the matter.
Interviewee: Yes, go ahead.
Interviewer: Further to the opinions you expressed in the questionnaire, please could you comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved. Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations.
Interviewee: In my experience, a contract which is wholly design and construct, or wholly construct only will have clearer design responsibilities than a contract which is construct only but with CDP's.
Interviewer: Can you expand on that?
Interviewee: To ensure that the parties understand their duties, clearly defined rules of engagement that are fair and reasonable for both parties need to be written into the contract.
Interviewer: Do you have any further comments?
Interviewee: Often the contract is let without the design being finalised, if it was, I feel as though the client team would probably choose a different form of contract.
Interviewer: Ok thank you for your time, good bye.
Interviewee: J
Profession: Project Manager
Experience: 28 Years
Duration: 0:0:42
Date: 17th March
Interviewer: As I’m sure you will know, I am just calling to gain a deeper understanding of your perspectives and options on the survey you participated in. If it is alright with you, I am going to pose a single question and if you wouldn’t mind discussing your thoughts on the matter.
Interviewee: Of course.
Interviewer: Further to the opinions you expressed in the questionnaire, please could you comment on the delineation of design culpability within construction contracts, the precision of the contractual terms and the intentions of those parties involved. Considering this, suggest how design could be accurately defined to ensure stakeholders understand their obligations.
Interviewee: Ok well to start with, the industry needs less adversarial contracts — regarding design responsibility — any designer that wishes to propose transfer of design responsibility should be forced to properly scope and specify the element concerned in the tender documents.
Interviewer: Thank you for your opinions of the subject, good bye.
[1] [1957] 1 WLR 582 (QB).
[2] [1957] 1 WLR 582 (QB).
[3] [1975] 3 ALL ER 99 (CA).
[4] [1975] 3 ALL ER 99 (CA).
[5] [1966] 4 BLR 50 (QB).
[6] [1966] 4 BLR 50 (QB).
[7] [1966] 4 BLR 50 (QB).
[8] [2010] EWCH 2300 (QB).
[9] [2010] EWCH 2300 (QB).
[10] [1981] 18 BLR 130 (CA).
[11] [2010] EWCH 2300 (QB).
[12] [1988] 38 BLR 25 (CA).
[13] [2015] BLR 431 (CA).
[14] [2015] BLR 431 (CA).
[15] [1968] 3 WLR 630 (HL).
[16] [1968] 3 WLR 630 (HL).
[17] [1975] 3 ALL ER 99 (CA).
[18] [1980] 14 BLR 1 (HL).
[19] [1980] 14 BLR 1 (HL).
[20] [1985] 33 BLR 103 (QB).
[21] [1985] 33 BLR 103 (QB).
[22] [2000] 3 NZLR 406 (CA).
[23] [2000] BLR 137 (CA).
[24] [1992] 62 BLR 147 (QB).
[25] [1838] 173 ER 581 (CP).
[26] [1838] 173 ER 581 (CP).
[27] [1975] 3 ALL ER 99 (CA).
[28] [1984] 128 SJ 969 (QB).
[29] [1974] 21 BLR 27 (SC).
[30] [1957] 2 WLR 583 (CA).
[31] [1990] AC 398 (HL).
[32] [1985] AC 80 (PC).
[33] [1932] AC 562 (HL).
[34] [1968] 442 621 (SC).
[35] [2012] EWHC 1972 (TCC).
[36] [2002] EWHC 1270 (QB).
[37] [1970] 3 CON LR 63 (DC).
Cite This Work
To export a reference to this article please select a referencing stye below:
Related Services
View allRelated Content
All TagsContent relating to: "Contract Law"
Contract law relates to documents that set out a legally binding agreement between two or more parties. The agreements, actions and stipulations contained within contracts are legally enforceable.